Miscellaneous action | | | 9/22/2011 | | DONE |
|
|
|
Sent to records for scanning.
|
INSP-Final Inspection | 8/19/2011 | 8/22/2011 | 8/22/2011 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 8/15/2011 | 8/18/2011 | 8/18/2011 | A | PART |
Forrest France
|
|
|
Items which remain for final include; provide spare heads at the head box of the type installed, certify the DCVA, re-test alarm and supervisory conditions at the riser. Final walkthrough completed acceptable.
|
INSP-Sprinkler Rough-in/Hydro | 8/2/2011 | 8/2/2011 | 8/2/2011 | P | PASS |
Troy Cobbley
|
|
|
Hydro test passed. Second floor piping can be covered.
|
Sprinkler Plan Check | 6/27/2011 | | 6/27/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 6/27/2011 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/27/2011 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 6/27/2011 | | 6/27/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 6/27/2011 | | DONE |
|
|
|
t/c w tony - permit (plan mod) ready and fees given
|
Permit Ready to Issue | | | 6/27/2011 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 6/27/2011 | | DONE |
Barbara Stitt
|
|
|
|
(F) Reprint permit | | | 6/27/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (Tim) | 6/24/2011 | | 6/27/2011 | | DONE |
Tim Frost
|
|
|
Plan modification
|
INSP-Sprinkler Rough-in | 6/23/2011 | 6/24/2011 | 6/24/2011 | A | PART |
Forrest France
|
|
|
Added upright sprinklers at the east end open office area soffit (due to ductwork obstructions) as marked and dated on approved plans okay for cover.
|
Plan resubmittals received | | | 6/24/2011 | | |
|
|
|
Plan modification
|
INSP-Sprinkler Rough-in/Hydro | 6/20/2011 | 6/22/2011 | 6/23/2011 | A | DONE |
Forrest France
|
|
|
Reference site inspection notes per T. Frost completed 6/22.
|
INSP-Sprinkler Rough-in/Hydro | 6/22/2011 | 6/23/2011 | 6/22/2011 | A | FAIL |
Troy Cobbley
|
|
|
Second floor only. The hydro passed. However, I also inspected the uprights in the soffit. Some of the sprinkers were blocked due to ductwork. Additional, sprinklers are required. Therefore the inspection failed.
|
Telephone call | | | 5/26/2011 | | DONE |
|
|
|
Spoke with Ron Amandus and Rick with Viking.
Per Ron they may demo the second floor provided the superintendent is set up as a day time fire watch. I told Rick the first floor system had to be maintained as operational. The only time the first floor system could be down was when they were working on the main riser. The first floor system cannot be down overnight without a fire watch.
|
Plan assigned to (Tim) | 5/13/2011 | | 5/25/2011 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 5/25/2011 | | 5/25/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/25/2011 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 5/25/2011 | | 5/25/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 5/25/2011 | | DONE |
|
|
|
t/c w tony - permit ready and fees given
|
Permit Ready to Issue | | | 5/25/2011 | | DONE |
|
|
|
|
Issue and Print Permit | | | 5/25/2011 | | DONE |
|
|
|
|
Plan resubmittals received | | | 5/23/2011 | | DONE |
Tisha Gallop
|
|
|
received four copies of application, submittal documents and plans; routed to Fire Review.
|
Sprinkler Plan Check | 5/17/2011 | | 5/17/2011 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 5/17/2011 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 5/17/2011 | | DONE |
|
|
|
Emailed review to contractor.
|
Telephone call | | | 5/17/2011 | | DONE |
|
|
|
t/c w tony - permit denied - needs to be picked up and resubmitted
|
Miscellaneous action | | | 5/17/2011 | | DONE |
Tisha Gallop
|
|
|
contractor picked up denied plans
|
Application received | | | 5/13/2011 | | |
|
|
|
|