Miscellaneous action | | | 1/20/2012 | | DONE |
|
|
|
Plans taken to records for scanning.
|
INSP-Final Inspection | 1/6/2012 | 1/9/2012 | 1/9/2012 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 1/6/2012 | 1/6/2012 | 1/6/2012 | P | CANC |
Troy Cobbley
|
|
|
rescheduled for monday
|
INSP-Final Inspection | 12/28/2011 | 12/30/2011 | 12/30/2011 | A | DEFR |
Forrest France
|
|
|
Please call Matt at ###-#### with inspection time. Phone #: ###-#### >> Inspection requested via web by Lori Brungardt
|
INSP-Final Inspection | 12/8/2011 | 12/9/2011 | 12/9/2011 | A | FAIL |
Troy Cobbley
|
|
|
Still need the Building A devices display and report as Building A as per the original correction notice.
|
INSP-Final Inspection | 10/27/2011 | 10/27/2011 | 10/27/2011 | P | FAIL |
Troy Cobbley
|
|
|
The underground conduit connecting the three buildings appears to be PVC and not the metallic conduit as stated on the plans. After confiring with Doug Poedy it was clear in both NFPA 72 and NEC that the only options for the interbuilding fire alarm circuiting are: provide a metalic cable shield (grounded to the building electrode system), run in metalic conduit (grounded to the building electrode system), or provide isolation modules. As-builts will be needed reflecting what is used. Will also need the netcom verified. Mount the building maps. Devices are labeled building "b" and "c" but not building "a". Relabel devices for building "a" so that consistancy is maintained. All other items have been checked.
|
CHANGE STATUS TO (ISS) | | | 10/10/2011 | | DONE |
Barbara Stitt
|
|
|
|
(F) Reprint permit | | | 10/10/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (Stephanie) | 9/29/2011 | | 10/7/2011 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Alarm Plan Check | 10/7/2011 | | 10/7/2011 | | PASS |
Stephanie L. Cobbley
|
|
|
Plan modification approved with redlines and review comments.
|
PLANS TAKEN FRONT DESK ALARM | | | 10/7/2011 | | DONE |
|
|
|
Approved redlined plan modification documents available at front counter.
|
Inspection Record Card- Fire | 10/7/2011 | | 10/7/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 10/7/2011 | | DONE |
|
|
|
t/c w lori - permit (plan mod) ready and fees given
|
Permit Ready to Issue | | | 10/7/2011 | | DONE |
|
|
|
|
Plan resubmittals received | | | 9/29/2011 | | DONE |
Tisha Gallop
|
|
|
Plan Modification: received two copies of application, submittal folder and plans; routed to Fire Review.
|
INSP-Final Inspection | 9/26/2011 | 9/26/2011 | 9/26/2011 | P | FAIL |
Troy Cobbley
|
|
|
Plan modifications need to be submitted due to door magnet installation and one line diagram not matching installation. The relays that are shown to activate the AES are actually releasing the doors. No testing was performed.
|
INSP-Final Inspection | 9/15/2011 | 9/16/2011 | 9/16/2011 | A | CANC |
Troy Cobbley
|
|
|
Cancel per Gary
|
Plan assigned to (Stephanie) | 6/22/2011 | | 7/1/2011 | | DONE |
Stephanie L. Cobbley
|
|
|
|
1st review completed | | | 7/1/2011 | | DONE |
|
|
|
|
Alarm Plan Check | 7/1/2011 | | 7/1/2011 | | PASS |
Stephanie L. Cobbley
|
|
|
Plans approved with redlines and review comments.
|
PLANS TAKEN FRONT DESK ALARM | | | 7/1/2011 | | DONE |
|
|
|
Approved redlined plans available at front counter.
|
Inspection Record Card- Fire | 7/1/2011 | | 7/1/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 7/1/2011 | | DONE |
|
|
|
t/c w terri - permit ready and fees given
|
Permit Ready to Issue | | | 7/1/2011 | | DONE |
|
|
|
|
Issue and Print Permit | | | 7/1/2011 | | DONE |
|
|
|
|
Application received | | | 6/22/2011 | | |
|
|
|
|