Miscellaneous action | | | 9/23/2013 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 11/20/2012 | 11/20/2012 | 11/20/2012 | A | PASS |
Forrest France
|
|
|
|
INSP-Final Inspection | 10/22/2012 | 10/22/2012 | 10/30/2012 | P | PEND |
Forrest France
|
|
|
Ref. activity notes.
|
INSP-Final Inspection | 10/17/2012 | 10/19/2012 | 10/30/2012 | A | PART |
Forrest France
|
|
|
Noted overspaced coverage at one location below ductwork at the junction between sub fab systems, provide verification AE and FE ductwork does not require protection per IFC 2009 1803.10.4 (1-3).
|
FIR-Aging Inspection | 8/28/2012 | 8/28/2012 | 8/28/2012 | | DEFR |
Forrest France
|
|
|
|
INSP-Supply line flush | 5/29/2012 | 5/30/2012 | 5/30/2012 | P | PART |
Forrest France
|
|
|
UG fire supply line flush for the SW building riser and remote FDC completed satisfactory.
|
INSP-Sprinkler Rough-in | 4/10/2012 | 4/11/2012 | 4/12/2012 | P | NR |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 4/2/2012 | 4/3/2012 | 4/4/2012 | P | PART |
Forrest France
|
|
|
Vestibules 000B and 002B are incomplete. Plan modifications pending.
|
INSP-Sprinkler Rough-in/Hydro | 3/30/2012 | 4/2/2012 | 4/2/2012 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic test passed.
|
INSP-Sprinkler Rough-in/Hydro | 3/29/2012 | 3/30/2012 | 3/30/2012 | P | NR |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 3/28/2012 | 3/29/2012 | 3/30/2012 | A | FAIL |
Forrest France
|
|
|
Overhead hydrostatic test failed due to pressure loss at the gauge.
|
INSP-Sprinkler Rough-in/Hydro | 2/28/2012 | 2/29/2012 | 3/1/2012 | P | PART |
Forrest France
|
|
|
Re-inspection for corrections system 8 sub fab include the following locations: added coverage at extended ductwork, over spacing at sub fab mechanical, coverage added at the catwalk and soffits between elevator machine room 001A and communication room 001B.
|
INSP-Sprinkler Rough-in/Hydro | 2/20/2012 | 2/21/2012 | 2/22/2012 | A | PART |
Forrest France
|
|
|
System 8 sub fab reinspection items include spacing at the temporary wall is 7'-6", four obstructed uprights adjacent to temporary unistrut trapeeze members, added outlet for chemical cabinets not shown on plans, missing potter air vent per drawings, added vestibules 000B and 002B including fire protection are not included on plans, sheetrock soffit enclosure at the new catwalk creates obstructions in three areas, need to add coverage under newly extended ductwork over 4', missing intermediate hangers under both stairways. Noted overspaced uprights under ductwork system 8 mechanical. Previous c/n items at some areas have been completed. Also noted quantities of sodium hypochlorite, sulfuric acid, process water, DI and IW located within the building.
|
INSP-Sprinkler Rough-in | 1/11/2012 | 1/12/2012 | 1/12/2012 | A | PART |
Forrest France
|
|
|
UG fire supply line flush at the NW riser feed completed satisfactory.
|
INSP-Supply line flush | 1/10/2012 | 1/11/2012 | 1/11/2012 | P | NR |
Forrest France
|
|
|
Contractor unable to complete supply line flushing at the NW riser due to jobsite conditions.
|
INSP-Sprinkler Rough-in/Hydro | 11/22/2011 | 11/23/2011 | 11/23/2011 | P | NR |
Forrest France
|
|
|
Please contact Jeremiah prior to arrival. Phone #: ###-#### >> Inspection requested via web by Alicia Pauley NOTE: **Area requested for inspection is not included in the scope of this permit (FIR11-00301 covers system 8 sub-fab). Contractor intended an overhead inspection for system 4 photo bay for which permit FIR11-00524 is not yet approved or issued at this time. Noted system 4 mains and branchlines already installed. No inspection performed due to permit status and lack of approved drawings.**
|
INSP-Sprinkler Rough-in | 11/21/2011 | 11/21/2011 | 11/21/2011 | P | PART |
Forrest France
|
|
|
UG fire supply line and remote FDC piping at the NW corner inspected prior to cover. Contractor has installed mechanical joint restraints in place of thrust blocks.
|
INSP-Sprinkler Rough-in/Hydro | 11/18/2011 | 11/21/2011 | 11/21/2011 | A | PART |
Forrest France
|
|
|
UG hydrostatic test for the NW fire supply line and remote FDC piping completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 11/18/2011 | 11/18/2011 | 11/18/2011 | P | NR |
Forrest France
|
|
|
Please call Jeremiah prior arrival to confirm. Phone #: ###-#### >> Inspection requested via web by Alicia Pauley
|
INSP-Sprinkler Rough-in | 11/14/2011 | 11/15/2011 | 11/15/2011 | A | PART |
Forrest France
|
|
|
UG fire supply line and remote FDC piping at the SE corner okayed to bury. Note: contractor has utilized a restrained joint system per NFPA 13 10.8.3 in place of thrust blocking. Discussed bury depth requirements with contractor per civil drawing elevations- UG pipe to be maintained 4'6" below grade min.
|
INSP-Sprinkler Rough-in/Hydro | 11/11/2011 | 11/14/2011 | 11/14/2011 | A | PART |
Forrest France
|
|
|
UG fire supply line and remote FDC piping at the SE corner of building 50 passed hydrostatic test.
|
INSP-Sprinkler Rough-in/Hydro | 11/9/2011 | 11/10/2011 | 11/10/2011 | A | FAIL |
Troy Cobbley
|
|
|
tony please call 1/2 hr prior Phone #: ###-####
Contacted tony and let him know I was on the way. I arrived and found that the water had not been turned on for tony to pump up the underground. No testing was performed.
|
Fees Due Hold | 10/13/2011 | | 10/14/2011 | | DONE |
Darla L Downs
|
|
|
|
CHANGE STATUS TO (ISS) | | | 8/26/2011 | | DONE |
|
|
|
|
Sprinkler Plan Check | 8/24/2011 | | 8/24/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 8/24/2011 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/24/2011 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 8/24/2011 | | 8/24/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 8/24/2011 | | DONE |
|
|
|
left vm for bob - permit (plan mod) ready and fees given
|
Permit Ready to Issue | | | 8/24/2011 | | DONE |
|
|
|
|
INSP-Conference | 8/12/2011 | 8/15/2011 | 8/15/2011 | A | DONE |
Forrest France
|
|
|
On site conference with contractor regarding project design, installation, schedule, etc.
|
Miscellaneous action | | | 7/26/2011 | | DONE |
|
|
|
Please, see below email regarding piping without continuous marking.
Ken,
Concerning the issue with 4” galvanized Schedule 40 pipe in area 8 at Micron Building 50. The pipe is supposed to be marked every 24” with manufacturing and listing data according to NFAP 13.
As per the documented Mill Report that indicates the 4” ASTM A53 Grade A Schedule 40 pipe passed the UL inspection and this particular batch of pipe was designated Heat #11123 and that the tags noted indicate that the pipe is ASTM A53 Grade A Schedule 40 and a UL symbol is on the tag and the tag also indicates that each of the 3 lifts is part of Heat #11123.
I believe this information is sufficient to be an alternative to the required markings and approve of the use of this pipe.
Thank You,
Ron Amandus
Interim Fire Marshal
Fire Prevention Division
Boise Fire Department
333 N. Mark Stall Place
Boise, Idaho 83###-####
###-####
|
Issue and Print Permit | | | 7/1/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (Tim) | 6/23/2011 | | 6/29/2011 | | DONE |
Tim Frost
|
|
|
|
Telephone call | | | 6/29/2011 | | DONE |
|
|
|
Spoke with Paul. He said the panels were non combustible aluminum. There will be a vesda detection system and smoke detection system. The smoke detection will be in the ductwork. They will be cross zoned.
|
Telephone call | | | 6/29/2011 | | DONE |
|
|
|
Talked with John Ronan and Paul. John informed me that the space below the raised floor would be non-combustible or limited combustible. Special composite materials are being utilized. I asked him about the 200 degree intermediate temperture sprinklers. He agreed that they should be regular temperture sprinklers not intermediate.
|
Sprinkler Plan Check | 6/29/2011 | | 6/29/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 6/29/2011 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/29/2011 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 6/29/2011 | | 6/29/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 6/29/2011 | | DONE |
|
|
|
left vm for bob - permit ready and fees given
|
Permit Ready to Issue | | | 6/29/2011 | | DONE |
|
|
|
|
Miscellaneous action | | | 6/28/2011 | | DONE |
|
|
|
Sent Paul an email and told him I still have not heard back from him in regards to the panels and flooring.
|
Telephone call | | | 6/27/2011 | | DONE |
|
|
|
I called Paul at Micron on Friday and left a voice mail. I called Paul at Micron again this morning. I asked him to tell me if the "1" Walkable Clean Room panels were combustible. He told me he would email me with the information. He also told me that he thought the panels and the floor above was perforated. I told him I was concerned that the response time of the sprinklers would be significantly impacted.
|
Application received | | | 6/23/2011 | | |
|
|
|
|