Miscellaneous action | | | 10/13/2011 | | DONE |
|
|
|
Plans taken to records for scanning.
|
INSP-Final Inspection | 9/6/2011 | 9/7/2011 | 9/7/2011 | A | PASS |
Forrest France
|
|
|
Corrections verified for completion. Fire alarm permit finaled.
|
INSP-Final Inspection | 8/31/2011 | 9/2/2011 | 9/2/2011 | A | FAIL |
Forrest France
|
|
|
Final pending repair of three non-functional waterflow switches at the new riser manifold.
|
INSP-Alarm Testing | 8/15/2011 | 8/15/2011 | 8/16/2011 | P | NR |
Forrest France
|
|
|
|
Issue and Print Permit | | | 8/9/2011 | | DONE |
|
|
|
|
Alarm Plan Check | 7/22/2011 | | 7/22/2011 | | PASS |
Stephanie L. Cobbley
|
|
|
Quick permit approved - no written review comments.
|
PLANS TAKEN FRONT DESK ALARM | | | 7/22/2011 | | DONE |
|
|
|
Approved quick permit plans available at front counter.
|
Inspection Record Card- Fire | 7/22/2011 | | 7/22/2011 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 7/22/2011 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 7/22/2011 | | DONE |
Tisha Gallop
|
|
|
called Fire Sentry, left message with answering service that permit is ready.
|
Plan assigned to (Stephanie) | 7/8/2011 | | 7/22/2011 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Plan assigned to (Stephanie) | 7/8/2011 | | 7/22/2011 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Plan resubmittals received | | | 7/20/2011 | | DONE |
|
|
|
|
Telephone call | | | 7/12/2011 | | DONE |
|
|
|
Left a message for John Lopez regarding descrepencies in the scope of work.
|
1st review completed | | | 7/12/2011 | | DONE |
|
|
|
|
Alarm Plan Check | 7/12/2011 | | 7/12/2011 | | FAIL |
Stephanie L. Cobbley
|
|
|
Resubmittal required. Show the backflow preventer tamper switch monitoring on the riser and calcs. If the flow switches are located in the stairwell of each floor, the monitor modules must be located with them and not all in the riser room as indicated. Ensure the application is signed and dated where shown (see page 3 of the application).
|
Miscellaneous action | | | 7/12/2011 | | DONE |
|
|
|
Faxed denied submittal to contractor
|
Telephone call | | | 7/11/2011 | | DONE |
|
|
|
Left a message for John Lopez regarding descrepencies in the scope of work.
|
Application received | | | 7/8/2011 | | |
|
|
|
|