Miscellaneous action | | | 12/16/2011 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 10/20/2011 | 10/20/2011 | 10/20/2011 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 10/18/2011 | 10/19/2011 | 10/19/2011 | A | CANC |
Troy Cobbley
|
|
|
Fire alarm contractor was not ready.
|
INSP-Final Inspection | 9/23/2011 | 9/23/2011 | 9/23/2011 | P | CANC |
Troy Cobbley
|
|
|
Could not perform testing of the fire alarm interconnections due to fire alarm panel issues.
|
INSP-Final Inspection | 9/16/2011 | 9/20/2011 | 9/20/2011 | A | FAIL |
Troy Cobbley
|
|
|
The 24 hour air test passed. The project can not be finaled until the inter connections with the fire alarm panel have been tested.
|
INSP-Sprinkler Rough-in/Hydro | 9/16/2011 | 9/19/2011 | 9/19/2011 | A | PASS |
Troy Cobbley
|
|
|
24 hour air test started at 8:30 am with 43 1/2 psi on the guage.
|
INSP-Final Inspection | 9/15/2011 | 9/16/2011 | 9/16/2011 | A | FAIL |
Troy Cobbley
|
|
|
Project is not ready for a final. Still need the fire alarm interconnections tested and the required 24 hour air test performed. Today we finished the rough-in for the remaining system and performed the forward flush which passed.
|
INSP-Final Inspection | 9/12/2011 | 9/12/2011 | 9/12/2011 | P | CANC |
Troy Cobbley
|
|
|
To be canceled per Jeff
|
INSP-Final Inspection | 9/9/2011 | 9/9/2011 | 9/9/2011 | P | CANC |
Forrest France
|
|
|
Overbooked
|
INSP-Supply line flush | 8/24/2011 | 8/25/2011 | 8/25/2011 | A | CANC |
Troy Cobbley
|
|
|
Could not do underground flush due to United Water
|
INSP-Sprinkler Rough-in/Hydro | 8/24/2011 | 8/25/2011 | 8/25/2011 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed.
|
INSP-Sprinkler Rough-in | 8/8/2011 | 8/9/2011 | 8/9/2011 | A | PASS |
Troy Cobbley
|
|
|
The "Tank Shop" sprinkler piping is ok to cover and rough-in is complete.
|
INSP-Sprinkler Rough-in | 8/4/2011 | 8/4/2011 | 8/4/2011 | P | PASS |
Troy Cobbley
|
|
|
Todays inspection was only for the attic sprinkler head lines. The rough-in on these were fine except Rick had to adjust the vertical elevation while I waited. I also posted a stop work order and a parcel hold due to the installation of sheet rock prior to approval and the installation of the sprinkler system at the west end of the building.
|
Plan assigned to (Tim) | 7/12/2011 | | 8/1/2011 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 8/1/2011 | | 8/1/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/1/2011 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 8/1/2011 | | 8/1/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 8/1/2011 | | DONE |
|
|
|
t/c w brodie - permit ready and fees given
|
Permit Ready to Issue | | | 8/1/2011 | | DONE |
|
|
|
|
Issue and Print Permit | | | 8/1/2011 | | DONE |
|
|
|
|
Plan resubmittals received | | | 7/28/2011 | | |
|
|
|
|
Sprinkler Plan Check | 7/14/2011 | | 7/14/2011 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 7/14/2011 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 7/14/2011 | | DONE |
|
|
|
Emailed review to contractor
|
Telephone call | | | 7/14/2011 | | |
|
|
|
left message with jeff for brodie - permit denied - needs to be picked up and resubmitted
|
Application received | | | 7/12/2011 | | |
|
|
|
|