Miscellaneous action | | | 12/16/2011 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 10/7/2011 | 10/10/2011 | 10/10/2011 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in | 8/29/2011 | 8/29/2011 | 8/29/2011 | P | PART |
Forrest France
|
|
|
Okay to cover the remainder of overhead work.
|
INSP-Sprinkler Rough-in/Hydro | 8/16/2011 | 8/17/2011 | 8/17/2011 | A | PART |
Forrest France
|
|
|
Okayed overhead rough-in at sheetrock lids adjacent to the restrooms and common corridors.
|
INSP-Sprinkler Rough-in | 8/3/2011 | 8/3/2011 | 8/3/2011 | P | PART |
Forrest France
|
|
|
Overhead work at the lobby area ceilings is approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 8/2/2011 | 8/2/2011 | 8/2/2011 | A | PART |
Forrest France
|
|
|
SW heads at the entry vestibule have been changed to pendents. New arm-overs and drops okayed for cover.
|
INSP-Sprinkler Rough-in | 7/22/2011 | 7/25/2011 | 7/25/2011 | A | PART |
Forrest France
|
|
|
Overhead fire sprinkler work at the sheetrock lids and soffits as marked on approved plan set okayed for cover. See dated annotations.
|
INSP-Sprinkler Rough-in | 7/22/2011 | 7/22/2011 | 7/22/2011 | P | PART |
Forrest France
|
|
|
|
Plan assigned to (Tim) | 7/18/2011 | | 7/21/2011 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 7/21/2011 | | 7/21/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 7/21/2011 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/21/2011 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 7/21/2011 | | 7/21/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 7/21/2011 | | DONE |
|
|
|
t/c w jeff packham - permit ready and fees given
|
Permit Ready to Issue | | | 7/21/2011 | | DONE |
|
|
|
|
Issue and Print Permit | | | 7/21/2011 | | DONE |
|
|
|
|
Application received | | | 7/18/2011 | | |
|
|
|
|