Miscellaneous action | | | 11/14/2011 | | DONE |
|
|
|
Plans taken to records for scanning.
|
INSP-Final Inspection | 11/4/2011 | 11/7/2011 | 11/7/2011 | P | PASS |
Forrest France
|
|
|
C/N items finished, plan modifications verified. Reinspection passed, fire alarm permit finaled.
|
Fees Due Hold | 10/22/2011 | | 11/4/2011 | | DONE |
Barbara Stitt
|
|
|
|
Inspection Record Card- Fire | 11/4/2011 | | 11/4/2011 | | DONE |
Barbara Stitt
|
|
|
|
Permit Ready to Issue | | | 11/4/2011 | | DONE |
Barbara Stitt
|
|
|
|
Issue and Print Permit | | | 11/4/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (Stephanie) | 10/31/2011 | | 11/3/2011 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Alarm Plan Check | 11/3/2011 | | 11/3/2011 | | PASS |
Stephanie L. Cobbley
|
|
|
Plan modification approved with redlines and review comments.
|
PLANS TAKEN FRONT DESK ALARM | | | 11/3/2011 | | DONE |
|
|
|
Approved redlined plan modification documents available at front counter.
|
INSP-Final Inspection | 10/12/2011 | 10/13/2011 | 10/13/2011 | A | FAIL |
Troy Cobbley
|
|
|
When testing the two second floor manual pull stations, as noted on the previous correction entry, I found that they reported to the panel as "zone 15". Per the plans they should be on zone 5. Per the technician all of the smoke detectors and manual pull stations on the second floor are on zone 15. The possible problem is per NFPA and the manufactures listing only a certain amount of powered devices can be placed on each zone. The new device count needs to be verified and if under the limits, as-builts and a new map at the facp is needed. If the count per circuit has been exceeded plan modifications are required. Also there is an issue with water flow alarms being sent from the new water flow switch. See the project related fire alarm permit for specifics.
|
INSP-Final Inspection | 10/5/2011 | 10/6/2011 | 10/6/2011 | P | FAIL |
Forrest France
|
|
|
Two non-functional MP stations at the 2nd floor need repaired, flow switch at the main riser is not operable. Notification testing, sprinkler riser supervision, new and relocated SD's tested okay.
|
INSP-Final Inspection | 8/23/2011 | 8/23/2011 | 8/25/2011 | P | NR |
Forrest France
|
|
|
|
Issue and Print Permit | | | 7/27/2011 | | DONE |
|
|
|
|
Plan assigned to (Stephanie) | 7/18/2011 | | 7/26/2011 | | DONE |
Stephanie L. Cobbley
|
|
|
|
1st review completed | | | 7/26/2011 | | DONE |
|
|
|
|
Alarm Plan Check | 7/26/2011 | | 7/26/2011 | | PASS |
Stephanie L. Cobbley
|
|
|
Approved with redlines and review comments.
|
PLANS TAKEN FRONT DESK ALARM | | | 7/26/2011 | | DONE |
|
|
|
Approved redlined plans available at front counter.
|
Inspection Record Card- Fire | 7/26/2011 | | 7/26/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 7/26/2011 | | DONE |
|
|
|
t/c w lisa - permit ready and fees given
|
Permit Ready to Issue | | | 7/26/2011 | | DONE |
|
|
|
|
Telephone call | | | 7/25/2011 | | DONE |
|
|
|
Ken with AEI requested that I switch the review order of this project with his other project; Grace Jordan Elementary (FIR11-00359) submitted on 7/20/11, due to time constraints.
|
Application received | | | 7/18/2011 | | |
|
|
|
|