Miscellaneous action | | | 4/24/2012 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 1/3/2012 | 1/4/2012 | 1/4/2012 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in | 12/7/2011 | 12/8/2011 | 12/8/2011 | A | PASS |
Troy Cobbley
|
|
|
The second floor office sprinkler piping is ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 11/30/2011 | 11/30/2011 | 11/30/2011 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test and flush passed.
|
INSP-Sprinkler Rough-in | 8/3/2011 | 8/4/2011 | 8/4/2011 | A | PASS |
Troy Cobbley
|
|
|
The underground supply piping is ok to cover. The installation of the tie in to the United water tap does not match plan and the fire aprinkler contractor decided not to install the PIV but to install a wall PIV. This change is to be shown on the overhead pipng submittals.
|
Miscellaneous action | | | 8/4/2011 | | DONE |
|
|
|
Email sent to TREASURE VALLEY FIRE PROTECTION
No resubmittal will be required. However, please, make sure the underground is accurately reflected on the above ground drawings when they are submitted.
Cordially,
Tim Frost, S.E.T.
Fire Sprinkler Plans Examiner
Fire Plans Examiner
Fire Inspector II
City of Boise
###-####
tfrost@cityofboise.org
>>> "Greg Patrick" 8/3/2011 1:41 PM >>>
Tim,
We had to make a modification to the site fire service configuration this morning. Due to the location of the existing service stub and other site complications, we had to move the service to the west approximately 10'-0". This change took the service out of the planter area requiring the deletion of the yard PIV. We will install a wall PIV at the fire riser room in lieu of the yard PIV. These changes will be clearly shown on the overhead submittal, forthcoming and are also shown on the as-built sketch attached. We have an inspection scheduled with Troy and are hopeful that this is an acceptable as-built scenario that will not require a full plan mod or resubmittal. Could you please review and confirm?
If you have any questions please call me. Thanks for your help.
|
Issue and Print Permit | | | 8/3/2011 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 7/28/2011 | | 8/2/2011 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 8/2/2011 | | 8/2/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 8/2/2011 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/2/2011 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 8/2/2011 | | 8/2/2011 | | DONE |
Darla L Downs
|
|
|
|
Permit Ready to Issue | | | 8/2/2011 | | DONE |
|
|
|
|
Telephone call | | | 8/2/2011 | | DONE |
|
|
|
8-2-11 called Greg left message permit ready and fee given ///dld
|
Application received | | | 7/28/2011 | | |
|
|
|
|