Miscellaneous action | | | 9/22/2011 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 9/13/2011 | 9/13/2011 | 9/13/2011 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 9/8/2011 | 9/9/2011 | 9/9/2011 | A | PART |
Forrest France
|
|
|
Fire sprinkler permit okay for final pending verification the existing system is current with and annual inspection per NFPA 25.
|
INSP-Sprinkler Rough-in/Hydro | 8/18/2011 | 8/18/2011 | 8/18/2011 | P | PART |
Forrest France
|
|
|
Modifications per the scope of work are approved for cover at both the grid and sheetrock ceiling areas.
|
Issue and Print Permit | | | 8/12/2011 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (Tim) | 8/8/2011 | | 8/11/2011 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 8/11/2011 | | 8/11/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/11/2011 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 8/11/2011 | | 8/11/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 8/11/2011 | | DONE |
|
|
|
t/c w don - permit ready and fees given
|
Permit Ready to Issue | | | 8/11/2011 | | DONE |
|
|
|
|
Plan resubmittals received | | | 8/10/2011 | | DONE |
Tisha Gallop
|
|
|
received three copies of application, submittal docs and plans; routed to fire review.
|
Sprinkler Plan Check | 8/9/2011 | | 8/9/2011 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 8/9/2011 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 8/9/2011 | | DONE |
|
|
|
Emailed contractor the review.
|
Telephone call | | | 8/9/2011 | | DONE |
|
|
|
t/c w don - permit denied - needs to be picked up and resubmitted
|
Miscellaneous action | | | 8/9/2011 | | DONE |
Tisha Gallop
|
|
|
denied plans picked up by contractor
|
Application received | | | 8/8/2011 | | |
|
|
|
|