Miscellaneous action | | | 6/4/2012 | | DONE |
|
|
|
Plans taken to records for scanning.
|
INSP-Final Inspection | 5/14/2012 | 5/14/2012 | 5/14/2012 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. Tim is mounting the map at the facp and providing me with the new version of NFPA 72 record of completion forms.
|
FIR-Aging Inspection | 4/19/2012 | 4/19/2012 | 4/20/2012 | | NR |
Troy Cobbley
|
|
|
Per Tim with Crane Alarm the hvac units are being repaired and the permit should be called in for inspection before too long.
|
INSP-Final Inspection | 9/2/2011 | 9/2/2011 | 9/2/2011 | P | FAIL |
Troy Cobbley
|
|
|
See the city approved plans for corrections marked in red. Signals for items tested today have been verified.
|
INSP-Alarm Testing | 9/1/2011 | 9/1/2011 | 9/2/2011 | P | CANC |
Troy Cobbley
|
|
|
Over booked.
|
Issue and Print Permit | | | 8/24/2011 | | DONE |
|
|
|
|
Plan assigned to (Stephanie) | 8/8/2011 | | 8/23/2011 | | DONE |
Stephanie L. Cobbley
|
|
|
|
1st review completed | | | 8/23/2011 | | DONE |
|
|
|
Waiting for requested documentation
|
Miscellaneous action | | | 8/23/2011 | | DONE |
|
|
|
Received requested documentation (2 sets)
|
Alarm Plan Check | 8/23/2011 | | 8/23/2011 | | PASS |
Stephanie L. Cobbley
|
|
|
Plans approved with redlines and review comments.
|
PLANS TAKEN FRONT DESK ALARM | | | 8/23/2011 | | DONE |
|
|
|
Approved redlined plans available at front counter.
|
Inspection Record Card- Fire | 8/23/2011 | | 8/23/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 8/23/2011 | | DONE |
|
|
|
t/c w jessica - permit ready and fees given
|
Permit Ready to Issue | | | 8/23/2011 | | DONE |
|
|
|
|
Telephone call | | | 8/22/2011 | | DONE |
|
|
|
Spoke to Tim Ezell at Crane Alarm. The records for this addres indicate there was an AES RF radio instead of a DACT. This submittal is to replace the panel, however phone lines are shown on the one-line diagram and no AES information was provided. Per Tim, they are going to re-use that existing AES panel. I explained that I would need all of the AES documentation as if it were new since they are not the company that installed it. He stated he would bring all of the information to me. I let him know that I could just red-line the riser diagram rather than have him resubmit since this is a panel replacement and needs to get taken care of ASAP.
|
Telephone call | | | 8/17/2011 | | DONE |
|
|
|
Left a message for Mary F. at ECI requesting the drawings for the submittal.
|
Application received | | | 8/8/2011 | | |
|
|
|
|
Early Start | | | 8/8/2011 | | DONE |
|
|
|
Early start request approved - see attached letter.
|