Miscellaneous action | | | 9/22/2011 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 9/20/2011 | 9/21/2011 | 9/21/2011 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit work approved for final.
|
INSP-Sprinkler Rough-in/Hydro | 9/20/2011 | 9/20/2011 | 9/20/2011 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic testing passed. Also verified relocated pendent heads at the second floor.
|
INSP-Final Inspection | 9/19/2011 | 9/19/2011 | 9/19/2011 | P | PART |
Forrest France
|
|
|
Verified matched temp. ratings. Final pending two relocated heads and hydrostatic test.
|
INSP-Sprinkler Rough-in | 9/14/2011 | 9/15/2011 | 9/16/2011 | A | PART |
Forrest France
|
|
|
Preliminary walkthrough completed, noted two heads at the second floor obstructed by adjacent soffits, some locations have mixed temp. heads within the same area minus specific heat source justification, hydrostatic testing will be required per NFPA 25 component action replacement table guidelines.
|
Plan assigned to (Tim) | 8/24/2011 | | 9/12/2011 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 9/12/2011 | | 9/12/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/12/2011 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 9/12/2011 | | 9/12/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 9/12/2011 | | DONE |
|
|
|
left vm for greg - permit ready and fees given
|
Permit Ready to Issue | | | 9/12/2011 | | DONE |
|
|
|
|
Issue and Print Permit | | | 9/12/2011 | | DONE |
|
|
|
|
Plan resubmittals received | | | 9/7/2011 | | DONE |
Christina Prado
|
|
|
Receive three sets of plan FP-1 as wells as applications and spec sheets. Plans given to Tim Frost for further review
|
Sprinkler Plan Check | 8/29/2011 | | 8/29/2011 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 8/29/2011 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 8/29/2011 | | DONE |
|
|
|
Emailed contractor review.
|
Telephone call | | | 8/29/2011 | | DONE |
|
|
|
left vm for greg patrick - permit denied - needs to be picked up and resubmitted
|
Application received | | | 8/24/2011 | | |
|
|
|
|