Description
This quick permit is for fire alarm phase 2 to add notification due to a tenant remodel. There are existing bathrooms that do not currently show notification, however they shall be provided under this permit (per conversation with the contractor). Inspector to field verify (please see redlined plans). Approval is subject to field measurement of the EOL voltage drop. For appliances with an operating voltage range of 16V – 33V, the minimum acceptable voltage is 19.6V with the AC power off. Any measurement below this voltage will be considered insufficient to run the NACs at the end of useful battery life of 20.4V. UL 864, Standard for Control Units for Fire Signaling Systems. The installing contractor shall have available at final inspection a voltage meter and measure end of line voltages; witnessed by the field inspector. There are no written review comments. Associated building permit: BLD11-00937 (GSA-DEPT OF AGRICULTURE – South East & North East corners of the Blue Heron Building) Permit is to remodel an existing 44,664 square foot office building. This building is fully fire sprinklered for area increase. Approval contingent upon adhering to the approved plans on file and plan review report. Work to include: [installation / demolition of interior partition walls to create a warehouse (S-1) area and multiple office/open office (B) areas], installation of a new floor sink, installation / relocation of new lighting, installation of new doors / accessible hardware, and finishes in compliance with chapter 8 of the 2009 IBC. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department.**TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  9/2/2011 DONE
Taken to records for scanning.
INSP-Final Inspection8/29/20118/29/20118/29/2011PPASS
DetailsTroy Cobbley
permit finaled
Issue and Print Permit  8/29/2011 DONE
Plan assigned to (Stephanie)8/25/2011 8/26/2011 DONE
DetailsStephanie L. Cobbley
Plan assigned to (Stephanie)8/25/2011 8/26/2011 DONE
DetailsStephanie L. Cobbley
Telephone call  8/26/2011 DONE
Spoke to Rob A. with Protex regarding the existing restrooms. They do not show notification on this submittal. I let Rob know that at some point before this building is finaled, this would need to be addressed and asked if he wants to cover the restrooms under this permit or one at a later date. He stated he wants to include them under this permit. I agreed to redline the plans and allow it to be a field verify. He said they would be wall mount devices.
1st review completed  8/26/2011 DONE
Alarm Plan Check8/26/2011 8/26/2011 PASS
DetailsStephanie L. Cobbley
Quick permit plans approved with redlines - no written review comments.
PLANS TAKEN FRONT DESK ALARM  8/26/2011 DONE
Approved redlined quick permit plans available at front counter.
Inspection Record Card- Fire8/26/2011 8/26/2011 DONE
DetailsPatricia Smith
Telephone call  8/26/2011 DONE
left vm for daric - permit ready and fees given
Permit Ready to Issue  8/26/2011 DONE
Details
Application received  8/25/2011