Permit Information
Permit NumberFIR11-00448
StatusFinaled
Name MICRON TECHNOLOGY INC FP
Site Address 8000 S FEDERAL WAY
Project NameB50-R&D EXPANSION BLD
Customer NumberC15044
ePlanReviewNo
Description
The Fire Sprinkler Scope of work consists of providing protection for the SubFab System 10 Mechanical. The system is a 4”x3”x2” grid.

Note: See related permits FIR11-00301, FIR11-00365, FIR11-00431

Plan Mod #1
Revised due to as built changes and design omissions. Removed (21) sprinklers from inside a duct near column T and between 17-4 as shown on drawing FP8. If the duct is conveying gases, vapors, fumes, mists or dust sprinklers ARE required inside the duct. If the duct is combustible nonmetallic sprinklers ARE required. . IFC: 1803.10.4
Field Inspector, please verify the duct above.

Plan Mod #1 Rev 1 7/13/2012, 7/18/2012, 7/30/2012
Revised due to as built changes. Added, new 3” express main
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  9/23/2013 DONE
DetailsTim Frost
Sent to Records for scanning.
INSP-Final Inspection12/19/201212/19/201212/19/2012APASS
DetailsForrest France
INSP-Final Inspection10/22/201210/22/201210/30/2012PPART
DetailsForrest France
Verified plan modifications, completed final walkthrough. Pending heads at fiberglass FE duct.
INSP-Final Inspection10/17/201210/18/201210/19/2012PNR
DetailsForrest France
INSP-Sprinkler Rough-in/Hydro10/17/201210/18/201210/19/2012APART
DetailsForrest France
Completed hydrostatic testing of the new 3" main.
CHANGE STATUS TO (ISS)  10/17/2012 DONE
DetailsTisha Gallop
Plan assigned to (Tim)10/5/2012 10/15/2012 DONE
DetailsTim Frost
Meeting  10/15/2012 DONE
Had a meeting with Collin, Paul, Jack of Micron and John Venchee. They comments in my previous reviews were discussed. Obstruction issues were partially resolved.
Sprinkler Plan Check10/15/2012 10/15/2012 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
PLANS/APPL TAKEN TO FRONT DESK  10/15/2012 DONE
DetailsTim Frost
Inspection Record Card- Fire10/15/2012 10/15/2012 DONE
DetailsBarbara Stitt
Permit Ready to Issue  10/15/2012 DONE
DetailsBarbara Stitt
Telephone call  10/15/2012 DONE
DetailsBarbara Stitt
Emailed Paul and told him that permit is ready & fees due on 10-15-12 @ 12:20pm//BAS
Telephone call  10/9/2012 DONE
Spoke with Collin. Told him I received the same information a fourth time. I told him I would not approve the design until my questions/review comments were answered.
Plan resubmittals received  10/5/2012  
Sprinkler Plan Check9/25/2012 9/25/2012 FAIL
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
Telephone call  9/25/2012 DONE
DetailsBarbara Stitt
Emailed Paul that plans were denied and need picked up and re-submitted on 9-25-12 @ 9:05am//BAS
Plan resubmittals received  9/19/2012  
Plan assigned to (Tim)7/27/2012 8/1/2012 DONE
DetailsTim Frost
Sprinkler Plan Check7/31/2012 7/31/2012 FAIL
DetailsTim Frost
Telephone call  7/31/2012 DONE
DetailsBarbara Stitt
Sent Paul Marsolina an email to pick up plans and resubmit on 7-31-12 @ 9:00am///BAS
Plan resubmittals received  7/27/2012 DONE
DetailsTisha Gallop
received three copies of sprinkler hydraulic calcs; routed to Fire
Plan resubmittals received  7/18/2012 DONE
DetailsChristina Prado
Received 3 new sets of plans. Gave to Tim for review
Plan resubmittals received  7/13/2012 DONE
DetailsChristina Prado
received three new sets of calcs and plans marked FP8 of 8. Routed to Tim for review
Sprinkler Plan Check4/23/2012 4/23/2012 FAIL
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
Telephone call  4/23/2012 DONE
DetailsBarbara Stitt
Emailed Paul that plans failed and need picked up and re-submitted on 4-23-12 @ 1:40pm//BAS
Plan assigned to (Tim)4/20/2012 4/23/2012 DONE
DetailsTim Frost
Plan resubmittals received  4/20/2012  
Plan Modification
INSP-Sprinkler Rough-in4/4/20124/4/20124/4/2012PPART
DetailsForrest France
Previous correction items including retainers and seismic bracing at mech. room 44, and overspaced coverage at N. mech. access finished. Plan modification pending.
INSP-Sprinkler Rough-in/Hydro3/30/20123/30/20123/30/2012APART
DetailsForrest France
Hydrostatic re-test of system 10 passed 3/29 PM.
INSP-Sprinkler Rough-in/Hydro3/28/20123/29/20123/30/2012AFAIL
DetailsForrest France
Overhead hydrostatic test failed due to pressure loss at the gauge. Noted re-inspection items include; plan resubmittal required due to: 18 additional upright heads not shown on the original design or included in the calculations, added 45's and 90's at the 4" grid mains, 2 1/2" main has been changed to 3", column protection is not included, missing longitudinal brace at mech. room 44, secure two retainers, upright coverage at the north mechanical access area is overspaced at 140ft2. Previous corrections finished are; sprig height at beams, axis adjustment, spacing at mechanical access 47 and south mech. access.
INSP-Sprinkler Rough-in/Hydro3/6/20123/7/20123/7/2012APART
DetailsForrest France
Inspection for cover at the new drop ceiling in the SW stair completed.
INSP-Sprinkler Rough-in/Hydro2/28/20123/1/20123/2/2012ANR
DetailsForrest France
>> Inspection requested via web by Alicia Pauley *Contractor unable to locate plan set*
INSP-Sprinkler Rough-in/Hydro2/28/20122/29/20122/28/2012ACANC
DetailsForrest France
Phone #: ###-#### >> Inspection requested via web by Alicia Pauley Inspection cancelled from web by: Alicia Pauley
INSP-Sprinkler Rough-in/Hydro2/20/20122/22/20122/23/2012AFAIL
DetailsForrest France
Refer to activity notes 2/23.
INSP-Sprinkler Rough-in/Hydro2/22/20122/23/20122/23/2012AFAIL
DetailsForrest France
System 10 inspection failed due to multiple deficiencies including; mechanical room 44- overspaced coverage at the west wall, five uprights below max. distance from the deck, missing seismic brace at 4" main, 3" main has been installed in place of 2 1/2" per the approved plan, 4" main installed on the opposite side of the beam, 6" feed main has been relocated, four 45 deg. ells have been added to the 4" main. Missing retainer at NW stair 60, four added 45 ells at S/W stair main. Mechanical access area- 4 upright heads exceed min. separation distances, added 90's at branchline, missing retainers, overspaced upright adjacent to division wall. Mechanical mezzanine 43- blocked heads at new beams, 10 added 90's at one 2" branchline, several sprig-ups are out of axis, noted approx. 15 added heads under various obstructions which are not included in the design. Access unavailable at one portion of the mechanical service area. Due to project schedule and a majority of plant process equipment already installed, some aspects of the system are not accessible for satisfactory inspection.
Fees Due Hold10/13/2011 10/14/2011 DONE
DetailsDarla L Downs
Issue and Print Permit  9/13/2011 DONE
Plan assigned to (Tim)8/26/2011 8/30/2011 DONE
DetailsTim Frost
Telephone call  8/30/2011 DONE
Spoke with Bob Knight. He said all of the ductwork and units shown on the drawing was on the roof which would be above the fire protection piping.
Sprinkler Plan Check8/30/2011 8/30/2011 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
1st review completed  8/30/2011 DONE
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  8/30/2011 DONE
DetailsTim Frost
Miscellaneous action  8/30/2011 DONE
Emailed Micro review
Inspection Record Card- Fire8/30/2011 8/30/2011 DONE
DetailsPatricia Smith
Telephone call  8/30/2011 DONE
t/c w bob - permit ready and fees given
Permit Ready to Issue  8/30/2011 DONE
Details
Application received  8/26/2011