Miscellaneous action | | | 9/27/2012 | | DONE |
|
|
|
plans taken to records for scanning
|
FIR-Aging Inspection | 9/19/2012 | 9/26/2012 | 9/26/2012 | A | PASS |
Troy Cobbley
|
|
|
Permit has beeen finaled
|
INSP-Final Inspection | 9/21/2012 | 9/24/2012 | 9/24/2012 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
Miscellaneous action | | | 9/20/2012 | | DONE |
|
|
|
Art with Tyco Integrated Security called to let me know they had lost their job-site copy. I took the plans to Idaho Blueprint to have them make a copy for Art to pick up.
|
FIR-Aging Inspection | 9/18/2012 | 9/18/2012 | 9/19/2012 | | NR |
Troy Cobbley
|
|
|
I stopped by the job site and spoke to Dana about getting this project inspected and finaled. A follow up inspection is scheduled for next week.
|
INSP-Conference | 4/20/2012 | 4/20/2012 | 4/20/2012 | P | DONE |
Troy Cobbley
|
|
|
Art and I discussed what I would need to complete the inspection for this project.
|
FIR-Aging Inspection | 4/12/2012 | 4/12/2012 | 4/20/2012 | | NR |
Troy Cobbley
|
|
|
Left voice mail for Dave with ADT requesting the project status.
|
Issue and Print Permit | | | 9/16/2011 | | |
|
|
|
|
Plan assigned to (Stephanie) | 9/6/2011 | | 9/12/2011 | | DONE |
Stephanie L. Cobbley
|
|
|
|
1st review completed | | | 9/12/2011 | | DONE |
|
|
|
|
Alarm Plan Check | 9/12/2011 | | 9/12/2011 | | PASS |
Stephanie L. Cobbley
|
|
|
Plans approved - see review comments
|
PLANS TAKEN FRONT DESK ALARM | | | 9/12/2011 | | DONE |
|
|
|
Approved plans available at front counter.
|
Inspection Record Card- Fire | 9/12/2011 | | 9/12/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 9/12/2011 | | DONE |
|
|
|
t/c w dave - permit ready and fees given
|
Permit Ready to Issue | | | 9/12/2011 | | DONE |
|
|
|
|
Case Summary | | | 9/6/2011 | | DONE |
Barbara Stitt
|
|
|
|
Application received | | | 9/6/2011 | | |
|
|
|
|