Permit Information
Permit NumberFIR11-00479
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 7009 W FRANKLIN RD
Project NameBishop Kelly
Customer Number 
ePlanReviewNo
Description
The Fire Sprinkler Scope of work consists of addition and remodeling of a portion of a school. The main riser will be relocated and new bulk main has been provided. A portion of the system is a grid with a side feed main. The remainder of the system is a tree. The construction is wood trusses therefore, there is above and below protection throughout.

The underground was modified under per FIR11-00299


Building Department Scope:

Bishop Kelly High School - Administration and Main Entry Remodel and Addition - To demolish and remove approximately 7,100 square feet of existing building that contains administrative offices and a storage garage area. To reconstructed that portion of the building to contain reconfigured administrative offices and accessible restrooms and to construct a 5,375 square foot addition that will contain a new main entry, lobby/study area, waiting area, new student commons and new men’s and women’s accessible restrooms. This permit also includes the construction of a new exterior entry plaza and other associate site improvements. This addition and remodel is being done on the northwest side of the high school. All construction shall be per the approved plans and attached comment list. JCM -TRF-
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  4/24/2012 DONE
DetailsTim Frost
Sent to Records for scanning.
INSP-Final Inspection2/15/20122/16/20122/16/2012APASS
DetailsTroy Cobbley
permit finaled
INSP-Final Inspection2/15/20122/15/20122/15/2012PFAIL
DetailsTroy Cobbley
Still need the zone map as discussed and signage on the bell and riser room door. Inspection rescheduled for tomorrow morning per conversation with CM company.
Miscellaneous action  2/15/2012 DONE
Received as built drawings and hydraulic calcualtions from the field inspector.
INSP-Sprinkler Rough-in2/13/20122/14/20122/14/2012APASS
DetailsTroy Cobbley
The sprinkler piping in Corridor 222 can be covered. As-builts are approved. To final the project a sticker is needed for the outside alarm bell, forward flush of the backflow, sprinkler work finished at the main entry/foirer and testing of the flow switches. Also a sprinkler system coverage/zone map is needed at the risers for fire dept use.
INSP-Final Inspection2/10/20122/13/20122/13/2012PCANC
DetailsTroy Cobbley
Can not final until previous corrections on wrong size piping and routing in remote area has been addressed.
INSP-Sprinkler Rough-in2/10/20122/13/20122/13/2012AFAIL
DetailsTroy Cobbley
The pipe size installed in Corridor 222 does not match the approved plans. Also per the fitter some pipe routing changes were needed in the remote area. Piping can not be covered.
INSP-Sprinkler Rough-in2/10/20122/10/20122/10/2012PFAIL
DetailsTroy Cobbley
The sprinkler fitter was not ready for an inspection. He will reschedule for monday.
INSP-Sprinkler Rough-in/Hydro1/24/20121/24/20121/24/2012PPASS
DetailsTroy Cobbley
The hydro test at the riser passed.
INSP-Sprinkler Rough-in/Hydro1/23/20121/24/20121/24/2012APART
DetailsTroy Cobbley
The hydro test for the system at the new lobby passed. The hydro test for the system at the new riser failed possibly due to the door to the riser room being left open. This test is rescheduled for this afternoon.
INSP-Sprinkler Rough-in1/20/20121/23/20121/23/2012PPASS
DetailsTroy Cobbley
All of the sprinkler piping in the new addition area located above the lay-in ceiling tile can be covered. The remodeled areas have not been inspected yet.
INSP-Conference1/19/20121/20/20121/20/2012PDONE
DetailsTroy Cobbley
Mike and I discussed not installing the two pendant heads in the soffit surrounding the sky light in the main entry/lobby. It is less than 4' at all points and typically only 18" wide. The sky light is covered by a sidewall sprinkler head. I'm ok with deleting the two soffit pendants. We also discussed scheduling cover inspections for the remaining areas
INSP-Sprinkler Rough-in12/14/201112/14/201112/16/2011PPASS
DetailsTroy Cobbley
The west side mens and womens restrooms are ok to cover
INSP-Sprinkler Rough-in12/2/201112/5/201112/5/2011APASS
DetailsTroy Cobbley
The city approved drawings were found and I compared them to the as-builts. They seem to match except that the two remote areas, Main Lobby and Banquette Room, are not shown on the as-builts.
INSP-Sprinkler Rough-in12/1/201112/2/201112/2/2011APART
DetailsTroy Cobbley
The overhead piping in the new addition area is complete except for the drops and the Main Entry area. These two items will need to be inspected when completed prior to a cover being given to cover the piping with the lay-in ceiling tile. The sprinkler piping above the hard lid areas of the new addition is ok for cover. The installation so far matches the provided as-builts. The city approved plans were not available and will need to be provided prior to any more inspections.
INSP-Sprinkler Rough-in11/28/201111/29/201111/28/2011ACANC
DetailsTroy Cobbley
Please call 1/2 hr prior to inspection. Leroy is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in11/23/201111/28/201111/28/2011PFAIL
DetailsTroy Cobbley
No city approved plans on site. The general contractor and I noted overspaced upright coverage along the east wall and in the riser room.
INSP-Conference11/4/201111/7/201111/7/2011ADONE
DetailsTroy Cobbley
Mike and I went over upright sprinkler spacing to the truss obstructions.
Issue and Print Permit  11/1/2011 DONE
Plan assigned to (Tim)9/7/2011 10/19/2011 DONE
DetailsTim Frost
Sprinkler Plan Check10/19/2011 10/19/2011 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
PLANS/APPL TAKEN TO FRONT DESK  10/19/2011 DONE
DetailsTim Frost
Inspection Record Card- Fire10/19/2011 10/19/2011 DONE
DetailsPatricia Smith
Telephone call  10/19/2011 DONE
t/c w melody - permit ready and fees given
Permit Ready to Issue  10/19/2011 DONE
Details
Plan resubmittals received  10/18/2011  
Case Summary  10/18/2011  
Sprinkler Plan Check10/13/2011 10/13/2011 FAIL
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
Miscellaneous action  10/13/2011 DONE
DetailsTim Frost
Emailed review to contractor
Telephone call  10/13/2011 DONE
t/c w melody - permit denied - needs to be picked up and resbumitted
Miscellaneous action  10/12/2011 DONE
Received the resubmittal letter per previous request.
Plan resubmittals received  10/11/2011  
Miscellaneous action  10/11/2011 DONE
Sent Shaun an email and told him I needed the resubmittal letter before the resubmittal review can begin.
Sprinkler Plan Check9/9/2011 9/9/2011 FAIL
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
1st review completed  9/9/2011 DONE
DetailsTim Frost
Miscellaneous action  9/9/2011 DONE
DetailsTim Frost
Emailed review to contractor
Application received  9/7/2011 DONE
DetailsBarbara Stitt