Miscellaneous action | | | 12/16/2011 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 10/4/2011 | 10/4/2011 | 10/4/2011 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 9/30/2011 | 10/3/2011 | 10/3/2011 | A | CANC |
Troy Cobbley
|
|
|
A new corridor wall marked "temporary" on the city approved building plans is going to be more of a permanent wall. Sprinkler protection will need to be added on the west side.
|
INSP-Sprinkler Rough-in | 9/22/2011 | 9/23/2011 | 9/23/2011 | A | PASS |
Troy Cobbley
|
|
|
Sprinkler piping is ok to cover
|
Plan assigned to (Tim) | 9/9/2011 | | 9/21/2011 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 9/21/2011 | | DONE |
|
|
|
Recevied additional information
|
Sprinkler Plan Check | 9/21/2011 | | 9/21/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 9/21/2011 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/21/2011 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 9/21/2011 | | 9/21/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 9/21/2011 | | DONE |
|
|
|
left vm for brodie - permit ready and fees given
|
Permit Ready to Issue | | | 9/21/2011 | | DONE |
|
|
|
|
Issue and Print Permit | | | 9/21/2011 | | DONE |
|
|
|
|
Miscellaneous action | | | 9/19/2011 | | DONE |
|
|
|
Sent email to Brodie as follows:
Provide a flow test within 6 months per NFPA 13.
Substantiate the pipe sizes are adequate for the use of Flex Heads based on current flow test information
This project is on hold until the above information is supplied.
|
Application received | | | 9/9/2011 | | |
|
|
|
|
Pending Assignment by SAM | 9/9/2011 | | 9/9/2011 | | DONE |
Patricia Smith
|
|
|
|