FIR-Aging Inspection | 5/11/2016 | 5/11/2016 | 5/18/2016 | | NR |
Troy Cobbley
|
|
|
Had the permit expired per scott and my discussion.
|
Permit EXPIRED | | | 5/18/2016 | | DONE |
|
|
|
per Scott Arellano and Troy Cobbley- never had inspections done. company went out of business.
|
FIR-Aging Inspection | 1/12/2016 | 1/12/2016 | 1/13/2016 | | NR |
Troy Cobbley
|
|
|
Contractor is out of business
|
FIR-Aging Inspection | 9/1/2015 | 9/1/2015 | 9/9/2015 | | NR |
Troy Cobbley
|
|
|
Contractor is out of business
|
FIR-Aging Inspection | 5/29/2015 | 5/29/2015 | 6/1/2015 | | NR |
Troy Cobbley
|
|
|
Contractor no longer in business
|
FIR-Aging Inspection | 9/9/2014 | 9/9/2014 | 9/9/2014 | | DONE |
Forrest France
|
|
|
|
FIR-Aging Inspection | 5/2/2014 | 5/2/2014 | 5/2/2014 | | DONE |
Forrest France
|
|
|
|
FIR-Aging Inspection | 5/7/2013 | 5/7/2013 | 5/7/2013 | | DONE |
Forrest France
|
|
|
|
FIR-Aging Inspection | 2/4/2013 | 2/4/2013 | 2/5/2013 | | DONE |
Forrest France
|
|
|
To Fire Dept.
|
FIR-Aging Inspection | 10/26/2012 | 10/26/2012 | 10/30/2012 | | DEFR |
Forrest France
|
|
|
Contractor no longer in business.
|
FIR-Aging Inspection | 4/27/2012 | 4/27/2012 | 4/27/2012 | | PEND |
Forrest France
|
|
|
Pending site inspection request for work completion.
|
Fees Due Hold | 10/13/2011 | | 10/14/2011 | | DONE |
Darla L Downs
|
|
|
|
Issue and Print Permit | | | 9/27/2011 | | DONE |
|
|
|
|
Plan assigned to (Stephanie) | 9/12/2011 | | 9/20/2011 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Plan assigned to (Stephanie) | 9/12/2011 | | 9/20/2011 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Miscellaneous action | | | 9/20/2011 | | DONE |
|
|
|
Requested information received
|
Alarm Plan Check | 9/20/2011 | | 9/20/2011 | | PASS |
Stephanie L. Cobbley
|
|
|
Quick permit approved with redlines - no written review comments.
|
PLANS TAKEN FRONT DESK ALARM | | | 9/20/2011 | | DONE |
|
|
|
Approved quick permit plans available at front counter.
|
Inspection Record Card- Fire | 9/20/2011 | | 9/20/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 9/20/2011 | | DONE |
|
|
|
left vm for ken - permit ready and fees given
|
Permit Ready to Issue | | | 9/20/2011 | | DONE |
|
|
|
|
Telephone call | | | 9/13/2011 | | DONE |
|
|
|
Spoke with Joe at Allied General regarding the scope of the project. The plans indicate that a "secondary alternate connection" is to be provided however there was no explaination as to what that "secondary alternate" is for. I asked Joe for clarification and he let me know that it is actually to provide the proper functions for the fireman's hat light. I requested revised documents that specify that it is for the fireman's hat light functions and also that the faxed documents are not legible and need to be revised so that the notes and alarm matrix can be easily read and scanned. He stated that he would need to get some clarification from the elevator installer and would get the information to me as soon as possible.
|
1st review completed | | | 9/13/2011 | | PEND |
|
|
|
Waiting for revised information and revised prints so the plans are legible.
|
Application received | | | 9/12/2011 | | |
|
|
|
|