Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR11-00503
StatusFinaled
Name SIMPLEX GRINNELL
Site Address 8055 W GODDARD RD
Project NameCAPITAL HIGH SCHOOL –FACP REPL
Customer Number 
ePlanReviewNo
Description
NOTE: There is an open fire alarm permit (FIR11-00379) for the remodeled admin area that must be finaled prior to beginning work on this permit scope.

This fire alarm permit is to replace the existing fire alarm panel with new. All existing devices and circuiting will remain the same, just re-landed on the new panel. A letter of agreement is on file indicating that the school’s intent is to gradually bring the fire alarm system up to current code requirements under separate permits. No devices are to be replaced or relocated, nor is circuiting to be changed under this permit. There is no associated building permit.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  4/16/2013 DONE
Plans taken to records for scanning
INSP-Final Inspection3/26/20133/27/20133/27/2013APASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection3/19/20133/26/20133/26/2013ACANC
DetailsTroy Cobbley
As early as possible Phone #: 2089411846 >> Inspection requested via mobile web by Brian Anderson Inspection cancelled via mobile web on Tuesday, March 26, 2013.
INSP-Final Inspection3/12/20133/19/20133/19/2013ACANC
DetailsTroy Cobbley
To be rescheduled for spring break
FIR-Aging Inspection11/26/201211/26/201211/29/2012 NR
DetailsTroy Cobbley
Charlie is going to try to schedule this for next week
FIR-Aging Inspection4/5/20124/5/20124/9/2012 DONE
DetailsTroy Cobbley
Was notified by the fire alarm plan reviewer that she has been contacted by an engineer about design issues for the school.
INSP-Final Inspection10/14/201110/17/201110/17/2011PFAIL
DetailsTroy Cobbley
Todays inspection was to finish up functional testing of the initiating devices. Due to my time constraints and only one contractor/tech we only had time to finish the second floor. Still need to check the portable classroom devices.
INSP-Final Inspection10/13/201110/14/201110/14/2011PFAIL
DetailsTroy Cobbley
Today's inspection was a partial test of the new fire alarm panel interconnection with the existing system circuits. Existing initiating devices tested today included most of the first floor main school building smoke detectors and manual pull stations. All tested items functioned and reported to the FACP. The items remaining to be tested include the gym, 2nd floor of the main building, and the portables. During inspection of the notification functionality, it was identified that parts of the building were temporal code and conflicted with surrounding areas that are steady tone. Per the original discussions, the entire existing building was reported to be steady tone, and that is why the new area was allowed to be installed to match. The areas with temporal include the auditorium and mixed devices throughout the rest of the school. This issue has been deferred to the plan reviewer and Scott Arellano. There is a non-functioning horn/strobe on the second floor that needs to be repaired. In addition, the gymnasium strobes are not synchronized and are newer system sensor devices. It is unclear if a permit was pulled for that work. Stephanie Cobbley is going to verify when synchronization started being required in code. Simplex is to let her know when the gym devices were installed. And finally, as-builts are required showing actual circuit call-outs since they are different than the contractor originally thought.
Issue and Print Permit  9/27/2011 DONE
Plan assigned to (Stephanie)9/13/2011 9/21/2011 DONE
DetailsStephanie L. Cobbley
1st review completed  9/21/2011 DONE
Alarm Plan Check9/21/2011 9/21/2011 PASS
DetailsStephanie L. Cobbley
Approved with redlines and review comments.
PLANS TAKEN FRONT DESK ALARM  9/21/2011 DONE
Approved redlined plans available at front counter.
Inspection Record Card- Fire9/21/2011 9/21/2011 DONE
DetailsPatricia Smith
Telephone call  9/21/2011 DONE
t/c w dante - permit ready and fees given
Permit Ready to Issue  9/21/2011 DONE
Details
Application received  9/13/2011