Information based on query as of Saturday, August 17, 2024.
Permit Information
Permit NumberFIR11-00524
StatusFinaled
Name MICRON TECHNOLOGY INC FP
Site Address 8000 S FEDERAL WAY
Project NameB50-R&D EXPANSION BLD
Customer Number 
ePlanReviewNo
Description
The Fire Sprinkler Scope of work consists of providing protection for System 4 Clean Room Photo Bay and Clean Link Photo Bay. The Clean Room Photo Bay part of the system is a 4”x4”x2” grid with a 6” feed main. The Clean Link Photo Bay has above and below protection which is supplied by two long 2” branch lines.

Note: See permit FIR11-00301, FIR11-00365, FIR11-0431, FIR11-00448 for the review on other portions of this building

Note: The nonclean link running through and parallel with column line 4 has not been included in this review.


Building Department Scope:

Micron Building B50 - R&D Building - To construct a new 111,005 square foot, two story, with 71,855 square foot basement, concrete and steel semiconductor fabrication R & D facility and related site improvements. The first floor level is 89, 435 sq. ft. (60,100 sq. ft. finished and 29,325 sq. ft. unfinished). The second floor is a 21,570 sq. ft. mechanical space (16,170 sq. ft. used and 5,400 square feet future). The basement level (subfab.) has 43,295 sq. ft. finished and 28,560 unfinished. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  9/23/2013 DONE
DetailsTim Frost
Sent to Records for scanning.
INSP-Final Inspection10/24/201210/24/201210/30/2012PPASS
DetailsForrest France
Corrections finished. Fire sprinkler permit finaled.
INSP-Final Inspection10/22/201210/22/201210/30/2012PPART
DetailsForrest France
Plan modifications and field install checked for equivalence.
INSP-Final Inspection10/17/201210/19/201210/30/2012APART
DetailsForrest France
Field verified corrections.
FIR-Aging Inspection7/3/20127/3/20127/3/2012 DONE
DetailsForrest France
CHANGE STATUS TO (ISS)  5/3/2012 DONE
DetailsTisha Gallop
Paul picked up plan mod
Case Summary  5/3/2012 DONE
DetailsTisha Gallop
Sprinkler Plan Check4/23/2012 4/23/2012 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
PLANS/APPL TAKEN TO FRONT DESK  4/23/2012 DONE
DetailsTim Frost
Inspection Record Card- Fire4/23/2012 4/23/2012 DONE
DetailsBarbara Stitt
CHANGE STATUS TO (ISS)  4/23/2012 DONE
DetailsBarbara Stitt
(F) Reprint permit  4/23/2012 DONE
DetailsBarbara Stitt
Telephone call  4/23/2012 DONE
DetailsBarbara Stitt
E-mailed paul that permit is ready & fees due on 4-23-12 @ 9:05am//BAS
Plan assigned to (Tim)4/20/2012 4/23/2012 DONE
DetailsTim Frost
Plan resubmittals received  4/20/2012  
Plan Modification
INSP-Sprinkler Rough-in4/2/20124/3/20124/4/2012PPART
DetailsForrest France
Previous C/N items verified for completion. Finished walkthrough for coverage adjustments at the overhead AMH tracks and cubbies. Noted missing coverage at the SW corner of the north half photo bay. Plan modifications pending.
INSP-Sprinkler Rough-in/Hydro3/28/20123/29/20123/30/2012APART
DetailsForrest France
System 4 overhead hydrostatic test passed. Completed re-inspection for relocated and added pendent heads at the AMH track areas. Noted missing hangers on three new arm-overs >2'.
INSP-Sprinkler Rough-in/Hydro2/28/20123/1/20123/2/2012PPART
DetailsForrest France
Re-inspection for noted correction items at system 4 photo bay and link include: retainers at mains and branchlines secured; adjustments in pendent head locations at AMH track underway- overhead storage cubbies may also present obstruction issues when installed; seismic bracing completed; pendent heads at the link drop ceiling are matched with grid install to date. Plans will need revised to reflect field modifications at several areas.
INSP-Sprinkler Rough-in/Hydro1/12/20121/13/20121/13/2012PFAIL
DetailsForrest France
Rough-in inspection completed for system # 4 clean link and photo bay. Noted items include missing retainers at several beam clamps on branchlines, 4" and 6" mains, missing hanger at arm-over, pendent heads are blocked or obstructed at numerous locations due to proximity to AMH brackets, flex head whips are not yet installed at various areas in the clean link, missing seismic bracing at the 6" main, secure EQ brace at the 4" main, added 90s at branchlines in the photo bay are not included in the calcs.- branch line restraint at these locations shall be provided per NFPA 13 9.3.6.4.
Fees Due Hold1/6/2012 1/6/2012 DONE
DetailsRita DeYoung
Fees Due Hold12/31/2011 1/5/2012 DONE
DetailsRita DeYoung
Fees Due Hold12/17/2011 12/30/2011 DONE
DetailsPatricia Smith
signed off per rita
Sprinkler Plan Check12/16/2011 12/16/2011 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
PLANS/APPL TAKEN TO FRONT DESK  12/16/2011 DONE
DetailsTim Frost
Permit Ready to Issue  12/16/2011 DONE
DetailsBarbara Stitt
Inspection Record Card- Fire12/16/2011 12/16/2011 DONE
DetailsBarbara Stitt
Telephone call  12/16/2011 DONE
DetailsBarbara Stitt
Called and left a message for Bob Knight that permit is ready & fees due on 12-16-11 @ 10:23AM
Issue and Print Permit  12/16/2011 DONE
Miscellaneous action  12/12/2011 PEND
Spoke with Jim Darr. He called back after saying he was providing trapeze hangers for the main. He now says he does not want to trapeze the mains. I told him if he wanted to hang the main from one truss that I would need a letter from a mechanical engineer indicating the truss will support the main. The project is on hold pending this information.
Plan resubmittals received  12/9/2011  
Received resubmittals 12-8-11
Plan assigned to (Tim)9/22/2011 12/6/2011 DONE
DetailsTim Frost
Miscellaneous action  9/29/2011 DONE
Micron picked up denied plans
Sprinkler Plan Check9/28/2011 9/28/2011 FAIL
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
1st review completed  9/28/2011 DONE
DetailsTim Frost
Miscellaneous action  9/28/2011 DONE
DetailsTim Frost
Emailed review to contractor
Telephone call  9/28/2011 DONE
t/c w tanner - permit denied - needs to be picked up and resubmitted
Telephone call  9/26/2011 DONE
Called John Ronan at Micron to discuss the design philospy of this project. Left a voice mail for him to call me back. The project is on hold pending his phone call.
Application received  9/22/2011  
INSP-Conference2/1/20122/3/2012 A 
DetailsForrest France
Phone #: ###-#### >> Inspection requested via web by Alicia Pauley