Miscellaneous action | | | 4/12/2012 | | DONE |
|
|
|
Plans taken to records for scanning
|
INSP-Final Inspection | 2/27/2012 | 3/1/2012 | 3/2/2012 | P | PASS |
Forrest France
|
|
|
Balance of acceptance test items completed. Corrections finished. Fire alarm permit finaled.
|
INSP-Final Inspection | 2/27/2012 | 2/29/2012 | 3/1/2012 | P | PART |
Forrest France
|
|
|
Completed device testing at all tenant rooms on the 1st thru 5th floors including ADA rooms and notification appliances in common and public areas. Items noted include four HD to be replaced, one tenant denied access for inspection purposes, cd settings at ADA rooms need adjusted. Provide as-built drawings.
|
INSP-Final Inspection | 2/23/2012 | 2/24/2012 | 2/24/2012 | P | PART |
Forrest France
|
|
|
Completed satisfactory retest of the elevator control functions after repairs made including the lobbies, pit and hoistway devices. Also finished acceptable testing of fire sprinkler monitoring including floor control valves, fire pump, MP station.
|
INSP-Alarm Testing | 2/23/2012 | 2/23/2012 | 2/24/2012 | A | PART |
Forrest France
|
|
|
|
INSP-Final Inspection | 2/17/2012 | 2/22/2012 | 2/22/2012 | P | NR |
Forrest France
|
|
|
robert - elevator final only Phone #: ###-#### * Rescheduled due to elevator malfunction during inspection *410
|
INSP-Final Inspection | 2/14/2012 | 2/15/2012 | 2/16/2012 | P | DEFR |
Forrest France
|
|
|
|
INSP-Alarm Testing | 2/13/2012 | 2/13/2012 | 2/13/2012 | A | PART |
Forrest France
|
|
|
Ref. plan annotations
|
INSP-Final Inspection | 2/9/2012 | 2/10/2012 | 2/10/2012 | P | PART |
Forrest France
|
|
|
Completed initial walkthrough. Noted items include two old system HD and five lobby SD to be removed, provide signage at the door to the FACP room, need lock at the control panel breaker, trash chute may require heat detection devices.
|
INSP-Final Inspection | 2/3/2012 | 2/6/2012 | 2/7/2012 | P | NR |
Forrest France
|
|
|
|
Issue and Print Permit | | | 10/14/2011 | | DONE |
|
|
|
|
Plan assigned to (Stephanie) | 10/7/2011 | | 10/13/2011 | | DONE |
Stephanie L. Cobbley
|
|
|
|
1st review completed | | | 10/13/2011 | | DONE |
|
|
|
|
Alarm Plan Check | 10/13/2011 | | 10/13/2011 | | PASS |
Stephanie L. Cobbley
|
|
|
Approved with redlines and review comments.
|
PLANS TAKEN FRONT DESK ALARM | | | 10/13/2011 | | DONE |
|
|
|
Approved redlined plans available at front counter
|
Inspection Record Card- Fire | 10/13/2011 | | 10/13/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 10/13/2011 | | DONE |
|
|
|
left message with shelly - permit ready and fees given
|
Permit Ready to Issue | | | 10/13/2011 | | DONE |
|
|
|
|
Application received | | | 10/7/2011 | | |
|
|
|
|