Miscellaneous action | | | 4/12/2012 | | DONE |
|
|
|
Plans taken to records for scanning
|
INSP-Final Inspection | 2/27/2012 | 3/1/2012 | 3/2/2012 | P | PASS |
Forrest France
|
|
|
Remainder of correction items verified for completion. Fire alarm permit finaled.
|
INSP-Final Inspection | 2/17/2012 | 2/22/2012 | 2/22/2012 | P | PART |
Forrest France
|
|
|
Completed satisfactory testing for the elevator control functions including machine room, hoistway and lobby SD and HD, shunt and control voltage monitor.
|
INSP-Final Inspection | 2/14/2012 | 2/17/2012 | 2/17/2012 | P | PART |
Forrest France
|
|
|
Completed testing for fire sprinkler monitoring including all floor control manifolds and pump room devices. Items noted include one non-functional TS at the 4th floor and two pump bypass tampers to be replaced.
|
INSP-Final Inspection | 2/9/2012 | 2/13/2012 | 2/14/2012 | P | PART |
Forrest France
|
|
|
Completed notification appliance testing 1st thru 7th floors, verified previous C/N items. Decibel levels at the 1st floor common restrooms exceed max. allowable- provide strobe only per plan at these locations. Verified visual coverage at all ADA rooms, provide WP appliances where noted.
|
INSP-Alarm Testing | 2/9/2012 | 2/9/2012 | 2/10/2012 | P | PART |
Forrest France
|
|
|
Completed testing of room heat detection devices throughout the 1st to 7th floors including system SD at ADA rooms. Noted items include 4 HD to be replaced, sync issues on the 7th floor, insufficient cd settings at ADA room notification appliances, four units in which access was denied for inspection purposes.
|
INSP-Final Inspection | 2/3/2012 | 2/6/2012 | 2/8/2012 | A | PART |
Forrest France
|
|
|
Verified previous correction items. Some issues remain including coverage at the 2nd floor operations office, raceway at the 4th floor, old system lobby SD's still in place, lock at FACP breaker. Alarm, trouble and supervisory signals were tested- however the zone 4 (supervisory) signals were undefined at central station monitoring. Discussed items remaining, inspection schedule, etc.
|
INSP-Alarm Testing | 1/24/2012 | 1/24/2012 | 1/24/2012 | A | PART |
Forrest France
|
|
|
|
INSP-Final Inspection | 1/18/2012 | 1/20/2012 | 1/24/2012 | P | PART |
Forrest France
|
|
|
Completed initial walkthrough. Noted items in need of adjustment, incompleted items such as the remote annunciator, record of inspection and testing forms, removal of old system horns, detectors, MP's. Discussed inspection schedule.
|
INSP-Final Inspection | 1/4/2012 | 1/5/2012 | 1/5/2012 | A | NR |
Forrest France
|
|
|
Robert Phone #: ###-####
|
Miscellaneous action | | | 11/9/2011 | | DONE |
|
|
|
After reviewing a phone call with the designer, it was agreed that the heat detectors in the units do not have to meet the 3' criteria for the bathroom doors but can not be mounted directly above a bathroom door. They do still need to meet the 3' rule for diffusers and air supplies.
|
Issue and Print Permit | | | 10/14/2011 | | DONE |
|
|
|
|
Plan assigned to (Stephanie) | 10/11/2011 | | 10/13/2011 | | DONE |
Stephanie L. Cobbley
|
|
|
|
1st review completed | | | 10/13/2011 | | DONE |
|
|
|
|
Alarm Plan Check | 10/13/2011 | | 10/13/2011 | | PASS |
Stephanie L. Cobbley
|
|
|
Plans approved with redlines and review comments.
|
PLANS TAKEN FRONT DESK ALARM | | | 10/13/2011 | | DONE |
|
|
|
Approved redlined plans available at front counter.
|
Inspection Record Card- Fire | 10/13/2011 | | 10/13/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 10/13/2011 | | DONE |
|
|
|
left message with shelly - permit ready and fees given
|
Permit Ready to Issue | | | 10/13/2011 | | DONE |
|
|
|
|
Application received | | | 10/11/2011 | | |
|
|
|
|