Miscellaneous action | | | 9/26/2012 | | DONE |
|
|
|
Plans taken to records for scanning.
|
INSP-Final Inspection | 7/2/2012 | 7/5/2012 | 7/6/2012 | P | PASS |
Forrest France
|
|
|
Noted correction items verified for completion. Fire alarm work passed acceptance testing. Permit finaled.
|
Fees Due Hold | 6/30/2012 | | 7/2/2012 | | DONE |
Christina Prado
|
|
|
|
INSP-Final Inspection | 6/27/2012 | 6/29/2012 | 6/29/2012 | A | FAIL |
Troy Cobbley
|
|
|
The city approved plans had been provided but the review comments and approved small document package was not available. The PIV tamper switch did not work. The sprinkler contractor was not available to test the two flow switches. The sleeping room smoke detectors did not sound a temporal signal as required per NFPA 72 29.3.5. The first floor corridor 104 smoke detector is labeled as Bay 1. As-builts need to be provided showing all of the changes and additions which include an AES panel instead of phone lines, an additional module for the AES trouble (point 17), and the flow switches are shown as tamper switches. A re-inspection fee has been applied.
|
INSP-Final Inspection | 6/25/2012 | 6/25/2012 | 6/25/2012 | P | FAIL |
Forrest France
|
|
|
See fire plan review notes item #1 regarding system smoke detectors at the sleeping rooms, tamper switch at the forward flow control valve is wired normally open, revise panel to eliminate the autotest communication error due to AES transmitter.
|
INSP-Final Inspection | 6/22/2012 | 6/22/2012 | 6/22/2012 | P | NR |
Forrest France
|
|
|
Johnathan or ###-#### Morgan Phone #: ###-#### Noted items include communication error at the panel, missing approved plans and review comments on site, butterfly valve at the forward flow does not need supervision, post signage at the door to the riser/FACP room, provide record of pre-testing.
|
FIR-Aging Inspection | 5/8/2012 | 5/8/2012 | 5/8/2012 | | DONE |
Forrest France
|
|
|
Construction underway. Site work in progress.
|
INSP-Conference | 1/18/2012 | 1/19/2012 | 1/19/2012 | A | DONE |
Forrest France
|
|
|
On site conference regarding location of the FACP and the MP station at the riser room to comply with NFPA 72 and NEC clearance and access guidelines.
|
Issue and Print Permit | | | 10/24/2011 | | DONE |
|
|
|
|
Telephone call | | | 10/21/2011 | | DONE |
|
|
|
left vm for dave - permit ready and fees given
|
Permit Ready to Issue | | | 10/21/2011 | | DONE |
|
|
|
|
Plan assigned to (Stephanie) | 10/17/2011 | | 10/20/2011 | | DONE |
Stephanie L. Cobbley
|
|
|
|
1st review completed | | | 10/20/2011 | | DONE |
|
|
|
|
Alarm Plan Check | 10/20/2011 | | 10/20/2011 | | PASS |
Stephanie L. Cobbley
|
|
|
Plans approved with redlines and review comments
|
PLANS TAKEN FRONT DESK ALARM | | | 10/20/2011 | | DONE |
|
|
|
Approved redlined plans available at front counter.
|
Inspection Record Card- Fire | 10/20/2011 | | 10/20/2011 | | DONE |
Patricia Smith
|
|
|
|
Application received | | | 10/17/2011 | | |
|
|
|
|
Reinspection Fee (no hold) | | 6/29/2012 | | | |
|
|
|
per 430 said he would call contractor to tell them fee was due.
|