Miscellaneous action | | | 9/26/2012 | | DONE |
|
|
|
Plans taken to records for scanning.
|
INSP-Final Inspection | 9/18/2012 | 9/18/2012 | 9/18/2012 | A | PASS |
Forrest France
|
|
|
Scope of fire alarm work completed, inspections passed. Permit final approved.
|
INSP-Alarm Testing | 8/15/2012 | 8/15/2012 | 8/15/2012 | P | PART |
Forrest France
|
|
|
Added heat detectors at the elevator machine room tested okay.
|
INSP-Final Inspection | 8/1/2012 | 8/1/2012 | 8/2/2012 | A | PART |
Forrest France
|
|
|
SD for elevator recall functions tested acceptable. Need to revise HD locations at the elevator machine room per NFPA 72 21.4.2.
|
INSP-Final Inspection | 4/23/2012 | 4/23/2012 | 4/23/2012 | A | PART |
Forrest France
|
|
|
Operational test of the fire curtain and acceptance testing per NFPA 80 completed. Re-inspection passed.
|
INSP-Sprinkler Rough-in | 4/16/2012 | 4/16/2012 | 4/19/2012 | P | PART |
Forrest France
|
|
|
Regarding relocated SD for door release service at the non-clean link bld 50 side.
|
INSP-Final Inspection | 4/17/2012 | 4/17/2012 | 4/19/2012 | P | PART |
Forrest France
|
|
|
|
INSP-Alarm Testing | 3/20/2012 | 3/20/2012 | 3/21/2012 | P | PART |
Forrest France
|
|
|
Duct system control valve descriptor and tamper switch at the yard PIV have been provided.
|
INSP-Alarm Testing | 3/19/2012 | 3/19/2012 | 3/19/2012 | A | PART |
Forrest France
|
|
|
Completed fire sprinkler monitoring test for systems installed to date- system 4,10,2, 8 duct and 8OH flows and tampers. Items noted include; incorrect descriptor at duct system 8 control valve, missing PIV tamper, one incomplete riser manifold, deluge valve for opening protection is unfinished.
|
INSP-Alarm Testing | 3/16/2012 | 3/16/2012 | 3/16/2012 | P | PART |
Forrest France
|
|
|
Completed testing for correction notice items dated 3/12. Also tested SD above FATC 5 and zones 1 thru 4 HSSD at the sub fab mechanical. Discussed sprinkler monitoring test and building 24D link testing schedule.
|
INSP-Alarm Testing | 3/13/2012 | 3/13/2012 | 3/16/2012 | P | PART |
Forrest France
|
|
|
Completed notification testing for project phase one areas including fabrication, cleanroom, mechanical, dock, and link corridors. Corrections and adjustments include; device location at mechanical room 44, obstructions to coverage at the mechanical deck due to equipment layout, one overspaced appliance at the service area above the photo bay, five TEM labs are below min. dB, insufficient visual coverage at the mechanical catwalks in two areas. Field inspection completed 3/12.
|
INSP-Alarm Testing | 3/8/2012 | 3/8/2012 | 3/9/2012 | A | PART |
Forrest France
|
|
|
Inspection items completed include; duct detectors at AHU's 5,6,7, SD above FATC at the mechanical level, MAU 1 and 2, and AHU 1 and 2 at the dock area.
|
INSP-Alarm Testing | 3/6/2012 | 3/7/2012 | 3/7/2012 | A | PART |
Forrest France
|
|
|
Today's inspection included under floor SD's at zones 4 and 5, clean link HSSD's at zones 1,2,3 and 4, HEPA shutdown at zones 1 thru 6 including program operations, duct detectors at mechanical mezzanine 43 and mech. room 44. Initiating device addresses and functionality tested okay. Noted one SD above the FATC in mech. room 44 to be relocated to the deck, MAU's at mech. mezzanine are not ready for shutdown test, discussed locations of duct detectors at the floor level east electrical room.
|
INSP-Alarm Testing | 3/5/2012 | 3/6/2012 | 3/6/2012 | A | PART |
Forrest France
|
|
|
Devices tested include SD's at panel, extender, underfloor detectors at zones 1,2,3 and 4.
|
INSP-Alarm Testing | 2/29/2012 | 3/2/2012 | 3/2/2012 | P | PART |
Forrest France
|
|
|
Completed initial walkthrough and partial testing for fire alarm work at sector 30 and sector 40 sub fab mechanical areas. Notification appliances and pull stations tested okay. Noted address needs assigned at the sw stair MP and accurate descriptor provided for the nw MP. Notification coverage in the fabrication areas may become obstructed as more process equipment is installed. Discussed associated permits for tool monitoring, vesdas, added tamper switches. Elevator control functions are incomplete at this time.
|
INSP-Conference | 1/24/2012 | 1/26/2012 | 1/26/2012 | A | DONE |
Forrest France
|
|
|
Regarding completion schedules for additional project related fire alarm permit work.
|
Issue and Print Permit | | | 12/5/2011 | | DONE |
|
|
|
|
Plan assigned to (Stephanie) | 10/19/2011 | | 11/29/2011 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Alarm Plan Check | 11/29/2011 | | 11/29/2011 | | PASS |
Stephanie L. Cobbley
|
|
|
Plans approved with redlines and review comments.
|
PLANS TAKEN FRONT DESK ALARM | | | 11/29/2011 | | DONE |
|
|
|
Approved redlined plans available at front counter.
|
Inspection Record Card- Fire | 11/29/2011 | | 11/29/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 11/29/2011 | | DONE |
|
|
|
t/c w dan - permit ready and fees given
|
Permit Ready to Issue | | | 11/29/2011 | | DONE |
|
|
|
|
Miscellaneous action | | | 11/25/2011 | | DONE |
|
|
|
I emailed Bryan Pepper requesting battery information for the VESDA systems as well as the fire alarm system.
|
1st review completed | | | 11/2/2011 | | DONE |
|
|
|
|
Alarm Plan Check | 11/2/2011 | | 11/2/2011 | | FAIL |
Stephanie L. Cobbley
|
|
|
Plans denied -see review comments and redlined plans
|
Miscellaneous action | | | 11/2/2011 | | DONE |
|
|
|
E-mailed Karyn Liles the plan review comments and let her know the plans have been denied. I stated in the e-mail that they would need to pick up the redlined plans and that they are available at the front counter.
|
Miscellaneous action | | | 11/2/2011 | | DONE |
|
|
|
Denied plans available at front counter.
|
Application received | | | 10/19/2011 | | |
|
|
|
|