Miscellaneous action | | | 4/24/2012 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 1/3/2012 | 1/4/2012 | 1/4/2012 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 12/19/2011 | 12/20/2011 | 12/20/2011 | P | PASS |
Troy Cobbley
|
|
|
24 hour air test and forward flush passed. First floor office area piping can be covered.
|
INSP-Sprinkler Rough-in/Hydro | 12/19/2011 | 12/19/2011 | 12/19/2011 | P | PASS |
Troy Cobbley
|
|
|
Wet and dry system hydro tests passed. The 24 hour air test was started at 2:00 with 42psi on the guage.
|
INSP-Sprinkler Rough-in/Hydro | 12/15/2011 | 12/16/2011 | 12/16/2011 | A | PASS |
Troy Cobbley
|
|
|
The rough-in inspection for all piping except for the first floor office area is passed. Mike needs to fix two retaining straps and provide flexible coupling at the top of all of the riser nipples. as shown on the approved plans. The piping in the dock area can be covered.
|
INSP-Sprinkler Rough-in/Hydro | 12/15/2011 | 12/15/2011 | 12/15/2011 | P | CANC |
Troy Cobbley
|
|
|
canceled due to time constraints
|
INSP-Sprinkler Rough-in | 12/8/2011 | 12/8/2011 | 12/8/2011 | P | PASS |
Troy Cobbley
|
|
|
The second floor office sprinkler piping can be covered.
|
INSP-Sprinkler Rough-in | 11/14/2011 | 11/15/2011 | 11/15/2011 | A | PASS |
Troy Cobbley
|
|
|
First and second floor hard lid areas are ok to cover. I noted that the sprinkler protection provided over the main entry canopy has not been installed. Mike is going to have his office contact me on this.
|
INSP-Sprinkler Rough-in | 11/9/2011 | 11/9/2011 | 11/9/2011 | P | PASS |
Troy Cobbley
|
|
|
The piping above the mens and womens 2nd floor restrooms is ok to cover.
|
Issue and Print Permit | | | 11/9/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (Tim) | 10/20/2011 | | 11/8/2011 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 11/8/2011 | | 11/8/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/8/2011 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 11/8/2011 | | 11/8/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 11/8/2011 | | DONE |
|
|
|
t/c w brad - permit ready and fees given
|
Permit Ready to Issue | | | 11/8/2011 | | DONE |
|
|
|
|
Plan resubmittals received | | | 11/4/2011 | | DONE |
Tisha Gallop
|
|
|
received application and three copies of submittal binder and plans; routed to Fire Review.
|
Sprinkler Plan Check | 10/27/2011 | | 10/27/2011 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 10/27/2011 | | DONE |
Tim Frost
|
|
|
|
Telephone call | | | 10/27/2011 | | DONE |
|
|
|
left vm for brad - permit denied - needs to be picked up and resubmitted
|
Miscellaneous action | | | 10/21/2011 | | DONE |
|
|
|
Sent combustible storage form to Brad for completion.
|
Application received | | | 10/20/2011 | | |
|
|
|
|
Case Summary | | | 10/20/2011 | | DONE |
|
|
|
|