Miscellaneous action | | | 10/11/2012 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 6/29/2012 | 6/29/2012 | 6/29/2012 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Alarm Testing | 6/28/2012 | 6/28/2012 | 6/28/2012 | A | PART |
Forrest France
|
|
|
Office phone #: ###-####
|
INSP-Sprinkler Rough-in | 6/14/2012 | 6/14/2012 | 6/14/2012 | P | PART |
Forrest France
|
|
|
Four new heads and related branchline piping at the new MRI room fed from the preaction system (project phase 3) are okay for cover.
|
INSP-Sprinkler Rough-in | 5/24/2012 | 5/24/2012 | 5/24/2012 | P | PART |
Forrest France
|
|
|
Overhead work at hall 212, room 214 and preaction system heads in the procedure room marked on stamped plans with today's date okayed for cover.
|
INSP-Sprinkler Rough-in | 4/16/2012 | 4/16/2012 | 4/16/2012 | P | PART |
Forrest France
|
|
|
Overhead work at the grid ceilings as marked on approved plans with today's date okayed for cover.
|
INSP-Sprinkler Rough-in | 3/23/2012 | 3/23/2012 | 3/23/2012 | P | PART |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 3/22/2012 | 3/22/2012 | 3/22/2012 | P | PART |
Forrest France
|
|
|
Overhead modifications at the control room and the work room okayed.
|
INSP-Sprinkler Rough-in | 2/14/2012 | 2/15/2012 | 2/15/2012 | A | PART |
Forrest France
|
|
|
Overhead work at the reception, blood draw, and nurse office remodel area phase one A approved for cover at the grid ceilings.
|
INSP-Sprinkler Rough-in | 1/5/2012 | 1/6/2012 | 1/6/2012 | A | PART |
Forrest France
|
|
|
Overhead work at the reception and entry vestibule sheetrock ceilings okayed for cover. Discussed heating issues and possible use of a dry pendent at the medical gas storage room.
|
INSP-Sprinkler Rough-in | 12/20/2011 | 12/21/2011 | 12/21/2011 | A | PART |
Forrest France
|
|
|
See areas on stamped plans marked and dated for rough-in approved at the new MRI room and west building addition.
|
Sprinkler Plan Check | 12/20/2011 | | 12/20/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/20/2011 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 12/20/2011 | | 12/20/2011 | | DONE |
Patricia Smith
|
|
|
|
Permit Ready to Issue | | | 12/20/2011 | | DONE |
|
|
|
|
Issue and Print Permit | | | 12/20/2011 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (Tim) | 11/2/2011 | | 12/20/2011 | | DONE |
Tim Frost
|
|
|
|
Early Start | | | 12/7/2011 | | PASS |
|
|
|
Requested because fire alarm submittal for the releasing system is out of Treasure Valley Fire Protection control and has not been submitted.
Request was approved.
|
Telephone call | | | 12/2/2011 | | DONE |
|
|
|
I jeft a message for Broide. There has been a fire alarm panel submittal, however, there were no releasing detectors shown on the drawing. Therefore, the preaction system would not be able to operate. The project is on hold pending new alarm drawings.
|
Plan resubmittals received | | | 11/29/2011 | | |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 11/7/2011 | | 11/7/2011 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 11/7/2011 | | DONE |
Tim Frost
|
|
|
|
Telephone call | | | 11/7/2011 | | DONE |
|
|
|
t/c w brodie - permit denied - needs to be picked up and resubmitted
|
Miscellaneous action | | | 11/7/2011 | | DONE |
Tisha Gallop
|
|
|
TV picked up denied plans
|
Application received | | | 11/2/2011 | | |
|
|
|
|