Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberFIR11-00607
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 2076 S CENTURY WAY
Project NameOXARC INC
Customer Number 
ePlanReviewNo
Description
The Fire Sprinkler Scope of work consists of a new fire protection with 8”x35’ C-900 underground piping, 6” backflow preventer, wall piv to a 6” feed/cross main to 1¼" branch lines. There is a nitrogen supplied dry system for the covered loading dock at the end of the 6” feed/cross main. The southeast corner of the building has flammable gas. This area has been designed for extra hazard. The remainder of the building is designed for ordinary hazard II. There are a number of control areas inside and outside the building.


Building Department Scope:

(OXARC INC) Remodel for a new tenant in an existing 10,520 sq. ft. building per approved plans. Building is 8,000 sq. ft. with a 2,520 covered dock area. Tenant use is for retail, filling, and storage of compressed gases with some office. NOTE: This building was originally constructed in Ada County and annexed into Boise City in 2002. Work to include: demolition work including the removal of an existing mezzanine per plans; construction of interior partitions walls creating; individual office areas, open office area, warehouse space, showroom, gas filling space, extinguisher area, charging room, hydro room, break room, electrical room, janitor room, and two new fully accessible restroom; install a new dual height (hi-lo) accessible drinking fountain; installation of a new storefront entry system; installation of new slot wall system on specific walls; new sales counter; new ADA ramp and dock area; installation of new suspended acoustical ceiling system; upgrade the lighting layout; interior finishes in compliance with chapter 8 of the 2009 IBC; new mechanical, new plumbing, and new electrical work; and all other work per the approved plans, attached plan review report, and all other reviewing agencies approvals. NOTE: This building will be fully fire sprinklered for area increase. A new Certificate of Occupancy with the new occupant load total is required to be obtained after all work has been inspected and approved and prior to tenant occupying this space. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  4/24/2012 DONE
DetailsTim Frost
Sent to Records for scanning.
INSP-Final Inspection4/12/20124/13/20124/13/2012APASS
DetailsTroy Cobbley
permit finaled. Forward flush passed.
INSP-Sprinkler Rough-in/Hydro4/4/20124/5/20124/5/2012APASS
DetailsTroy Cobbley
Overhead hydro test passed
INSP-Supply line flush4/4/20124/4/20124/4/2012PPASS
DetailsTroy Cobbley
Underground flush passed.
INSP-Conference3/15/20123/15/20123/15/2012PDONE
DetailsTroy Cobbley
I spoke to jeff about an additional fitting and elevation change in the piping out on the dock. He was going to get with his designer and then with Tim Frost to verify that the hydraulic calculations were still acceptable.
Miscellaneous action  3/15/2012 DONE
Recevied new hydraulic calculation for remote area 4. Due to field conditions additional fittings were added. The new demand is 1528.12@50.604 with a safety factor of 5.04, Therefore the hydraulics are acceptable.
INSP-Sprinkler Rough-in3/14/20123/14/20123/14/2012PPASS
DetailsTroy Cobbley
The sprinkler piping above the lay-in tile areas can be covered.
INSP-Sprinkler Rough-in3/9/20123/12/20123/12/2012AFAIL
DetailsTroy Cobbley
The plans were locked up in the job trailer. General contractor was not on site. Could not perform inspection. Left message on Don's voice mail.
INSP-Sprinkler Rough-in/Hydro2/29/20122/29/20123/1/2012PPASS
DetailsTim Frost
Underground Hydro test passed
INSP-Sprinkler Rough-in2/3/20122/6/20122/6/2012APASS
DetailsTroy Cobbley
Hard lid areas are ok to cover.
INSP-Sprinkler Rough-in/Hydro12/20/201112/21/201112/21/2011APASS
DetailsTroy Cobbley
24 hour air test passed
INSP-Sprinkler Rough-in12/20/201112/21/201112/21/2011APASS
DetailsTroy Cobbley
24 hour air test passed
INSP-Sprinkler Rough-in12/20/201112/20/201112/20/2011PPASS
DetailsTroy Cobbley
24 hr pressure test started 10:00 with 42 1/2 psi
INSP-Sprinkler Rough-in12/13/201112/13/201112/13/2011PPASS
DetailsTroy Cobbley
Todays inspection was for the hanger attachments at the purlins. The hanger attachment points can be covered with insulation.
INSP-Supply line flush12/9/201112/9/201112/9/2011PPASS
DetailsTroy Cobbley
The underground supply piping is ok to cover. No flush was performed.
Permit Ready to Issue  11/28/2011 DONE
DetailsBarbara Stitt
Issue and Print Permit  11/28/2011 DONE
DetailsBarbara Stitt
Plan assigned to (Tim)11/14/2011 11/23/2011 DONE
DetailsTim Frost
Miscellaneous action  11/23/2011 DONE
Recevied revised drawings due to a conversation with Jeff. We aggree that the most remote area needed to be configured differently.
Sprinkler Plan Check11/23/2011 11/23/2011 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
1st review completed  11/23/2011 DONE
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  11/23/2011 DONE
DetailsTim Frost
Inspection Record Card- Fire11/23/2011 11/23/2011 DONE
DetailsPatricia Smith
Application received  11/14/2011