Miscellaneous action | | | 4/24/2012 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 4/12/2012 | 4/13/2012 | 4/13/2012 | A | PASS |
Troy Cobbley
|
|
|
permit finaled. Forward flush passed.
|
INSP-Sprinkler Rough-in/Hydro | 4/4/2012 | 4/5/2012 | 4/5/2012 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed
|
INSP-Supply line flush | 4/4/2012 | 4/4/2012 | 4/4/2012 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed.
|
INSP-Conference | 3/15/2012 | 3/15/2012 | 3/15/2012 | P | DONE |
Troy Cobbley
|
|
|
I spoke to jeff about an additional fitting and elevation change in the piping out on the dock. He was going to get with his designer and then with Tim Frost to verify that the hydraulic calculations were still acceptable.
|
Miscellaneous action | | | 3/15/2012 | | DONE |
|
|
|
Recevied new hydraulic calculation for remote area 4. Due to field conditions additional fittings were added. The new demand is 1528.12@50.604 with a safety factor of 5.04, Therefore the hydraulics are acceptable.
|
INSP-Sprinkler Rough-in | 3/14/2012 | 3/14/2012 | 3/14/2012 | P | PASS |
Troy Cobbley
|
|
|
The sprinkler piping above the lay-in tile areas can be covered.
|
INSP-Sprinkler Rough-in | 3/9/2012 | 3/12/2012 | 3/12/2012 | A | FAIL |
Troy Cobbley
|
|
|
The plans were locked up in the job trailer. General contractor was not on site. Could not perform inspection. Left message on Don's voice mail.
|
INSP-Sprinkler Rough-in/Hydro | 2/29/2012 | 2/29/2012 | 3/1/2012 | P | PASS |
Tim Frost
|
|
|
Underground Hydro test passed
|
INSP-Sprinkler Rough-in | 2/3/2012 | 2/6/2012 | 2/6/2012 | A | PASS |
Troy Cobbley
|
|
|
Hard lid areas are ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 12/20/2011 | 12/21/2011 | 12/21/2011 | A | PASS |
Troy Cobbley
|
|
|
24 hour air test passed
|
INSP-Sprinkler Rough-in | 12/20/2011 | 12/21/2011 | 12/21/2011 | A | PASS |
Troy Cobbley
|
|
|
24 hour air test passed
|
INSP-Sprinkler Rough-in | 12/20/2011 | 12/20/2011 | 12/20/2011 | P | PASS |
Troy Cobbley
|
|
|
24 hr pressure test started 10:00 with 42 1/2 psi
|
INSP-Sprinkler Rough-in | 12/13/2011 | 12/13/2011 | 12/13/2011 | P | PASS |
Troy Cobbley
|
|
|
Todays inspection was for the hanger attachments at the purlins. The hanger attachment points can be covered with insulation.
|
INSP-Supply line flush | 12/9/2011 | 12/9/2011 | 12/9/2011 | P | PASS |
Troy Cobbley
|
|
|
The underground supply piping is ok to cover. No flush was performed.
|
Permit Ready to Issue | | | 11/28/2011 | | DONE |
Barbara Stitt
|
|
|
|
Issue and Print Permit | | | 11/28/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (Tim) | 11/14/2011 | | 11/23/2011 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 11/23/2011 | | DONE |
|
|
|
Recevied revised drawings due to a conversation with Jeff. We aggree that the most remote area needed to be configured differently.
|
Sprinkler Plan Check | 11/23/2011 | | 11/23/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 11/23/2011 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/23/2011 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 11/23/2011 | | 11/23/2011 | | DONE |
Patricia Smith
|
|
|
|
Application received | | | 11/14/2011 | | |
|
|
|
|