Miscellaneous action | | | 10/11/2012 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 7/3/2012 | 7/3/2012 | 7/5/2012 | P | PASS |
Forrest France
|
|
|
Final walkthrough and acceptance test passed. Two missing escutcheons installed while on site. Fire sprinkler permit finaled.
|
INSP-Sprinkler Rough-in | 4/27/2012 | 4/30/2012 | 4/30/2012 | P | PART |
Forrest France
|
|
|
Overhead modifications at the beam pockets per previous inspection notes approved for cover.
|
INSP-Sprinkler Rough-in | 4/20/2012 | 4/20/2012 | 4/20/2012 | P | DONE |
Troy Cobbley
|
|
|
Lonnie had concerns over the two beams blocking pendant sprinkler coverage in the "Great Room". I met the general contractor and showed him the obstruction charts in NFPA 13D. It appears that the best option is three addtional heads in the center beam pocket.
|
INSP-Sprinkler Rough-in | 1/4/2012 | 1/4/2012 | 1/4/2012 | A | PART |
Forrest France
|
|
|
Overhead rough-in only okayed for cover.
|
INSP-Sprinkler Rough-in | 12/29/2011 | 12/30/2011 | 12/30/2011 | A | PART |
Forrest France
|
|
|
Verified coverage adjustments at the excersise room. Inspection for cold cavity protection completed satisfactory. OH rough-in approved for cover.
|
INSP-Sprinkler Rough-in | 12/21/2011 | 12/22/2011 | 12/22/2011 | A | PART |
Forrest France
|
|
|
Overhead rough-in passed with the exception of two pendent heads at the 2nd floor excersise room to be relocated due to ceiling fan obstructions. Inspection for cold cavity protection required prior to cover approval.
|
Issue and Print Permit | | | 12/19/2011 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/15/2011 | | 12/15/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 12/15/2011 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/15/2011 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 12/15/2011 | | 12/15/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 12/15/2011 | | DONE |
|
|
|
left vm for jon - permit ready and fees given
|
Permit Ready to Issue | | | 12/15/2011 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 11/29/2011 | | 12/15/2011 | | DONE |
Tim Frost
|
|
|
|
Plan resubmittals received | | | 12/14/2011 | | |
|
|
|
12-14-11 received 3 sets of plans sent to Tim F
|
Miscellaneous action | | | 12/12/2011 | | DONE |
Tisha Gallop
|
|
|
contractor picked up denied plans
|
Sprinkler Plan Check | 12/9/2011 | | 12/9/2011 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
Telephone call | | | 12/9/2011 | | DONE |
Barbara Stitt
|
|
|
Called left voice message for Jon Edes that plan was denied on 12-9-11 @ 2:00pm//BAS
|
Plan resubmittals received | | | 12/7/2011 | | |
|
|
|
|
Miscellaneous action | | | 12/2/2011 | | DONE |
|
|
|
picked up denied plans
|
Sprinkler Plan Check | 12/1/2011 | | 12/1/2011 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 12/1/2011 | | DONE |
Tim Frost
|
|
|
|
Telephone call | | | 12/1/2011 | | DONE |
|
|
|
left vm for jon - permit denied - needs to be picked up and resubmitted
|
Application received | | | 11/29/2011 | | |
|
|
|
|