Miscellaneous action | | | 9/23/2013 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 4/23/2012 | 4/23/2012 | 4/23/2012 | P | PASS |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 2/28/2012 | 2/29/2012 | 3/1/2012 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic test and rough-in inspection completed acceptable.
|
INSP-Sprinkler Rough-in/Hydro | 2/24/2012 | 2/24/2012 | 2/24/2012 | P | DEFR |
Forrest France
|
|
|
Intended for hydrostatic testing of the new system supply main.
|
Issue and Print Permit | | | 12/16/2011 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 12/12/2011 | | 12/15/2011 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 12/15/2011 | | 12/15/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 12/15/2011 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/15/2011 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 12/15/2011 | | 12/15/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 12/15/2011 | | DONE |
|
|
|
left vm for karyn - permit ready and fees given
|
Permit Ready to Issue | | | 12/15/2011 | | DONE |
|
|
|
|
Telephone call | | | 12/14/2011 | | PEND |
|
|
|
Spoke with Colin and asked him to send manufacture literature on the strainer. Project is on hold pending this information.
|
Application received | | | 12/12/2011 | | |
|
|
|
|