Miscellaneous action | | | 9/27/2012 | | DONE |
|
|
|
Plans taken to records for scanning
|
INSP-Final Inspection | 8/14/2012 | 8/16/2012 | 8/16/2012 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Alarm Testing | 8/7/2012 | 8/9/2012 | 8/9/2012 | P | PASS |
Troy Cobbley
|
|
|
Testing 1st and 2nd Floor of area "C" passed. To final the project a map is needed at the facp as discussed. Need signage on doors as well.
|
INSP-Alarm Testing | 7/25/2012 | 7/27/2012 | 7/27/2012 | A | PASS |
Troy Cobbley
|
|
|
Todays testing included the 3rd and 4th floors of Area "C" which passed.
|
INSP-Alarm Testing | 7/24/2012 | 7/25/2012 | 7/25/2012 | P | CANC |
Troy Cobbley
|
|
|
Cancel per Matt Casey due to flooring being installed and elevator problems.
|
INSP-Alarm Testing | 7/2/2012 | 7/3/2012 | 7/3/2012 | A | DONE |
Troy Cobbley
|
|
|
Fire alarm complete for area "A" and "B" 3rd and 4th floors. A relay and a horn were replaced during the inspection.
|
INSP-Alarm Testing | 6/28/2012 | 6/28/2012 | 6/28/2012 | A | DONE |
Troy Cobbley
|
|
|
Todays inspection was for the 3rd and 4th for Towers 1 and 2. The third floor fire/smoke damper smoke detector needs to be replaced and re-tested. Also rooms at the fire wall separation on both the third and fourth floors did not operate due to work being completed on the other side of the fire wall. These circuits need to be complete before a sign off for the third and fourth floor areas.
|
INSP-Alarm Testing | 6/19/2012 | 6/19/2012 | 6/19/2012 | P | PASS |
Troy Cobbley
|
|
|
East wing tamper valve for Shilo Sprinkler passed functional testing.
|
INSP-Alarm Testing | 6/13/2012 | 6/14/2012 | 6/14/2012 | A | DONE |
Troy Cobbley
|
|
|
The fire alarm testing is complete for the area "A" and "B", first and second floors.
|
INSP-Alarm Testing | 6/12/2012 | 6/13/2012 | 6/13/2012 | A | DONE |
Troy Cobbley
|
|
|
Todays inspection included reverification of the fire smoke damper activation and the west side elevator recall. Also incuded were EOL voltage verification for areas "A" and "B", first and second floor audio/visuals. To finish these this area I need the horns in rooms 215 and 220 repaired and test the separate notification circuits at the first and second floor fire wall in area "B".
|
INSP-Alarm Testing | 6/11/2012 | 6/11/2012 | 6/11/2012 | P | DONE |
Troy Cobbley
|
|
|
Todays testing was for the first and second floor fire door smoke detectors in the west wing (area A). Both relays had to be replaced while I waited. The relay was also replaced at the smoke detector/smoke damper at the first floor, west elevator. The programing needs changes so that upon alarm silence the dampers do not open. Could not test the elevators since the reset key was not available.
|
INSP-Alarm Testing | 6/6/2012 | 6/8/2012 | 6/8/2012 | P | DONE |
Troy Cobbley
|
|
|
Todays inspection verified the facp and nac panels. Also tested were the fire sprinkler interconnections Devices tested ok but several have different addresses and locations. The nac wireing includes 18 guage from the panel to the sync modules then back to the nac can then continues to the nac circuits with 12 guage wire. I will need to speak to plan review if this will be allow with EOL verification. The fire alarm system currently has multiple trouble and ground faults being displayed. Also no sprinkler head has been installed in the elevator equipment rooms. The heat detector can be deleted but the smoke will remain for alternate recall.
|
FIR-Aging Inspection | 6/5/2012 | 6/5/2012 | 6/5/2012 | | NR |
Troy Cobbley
|
|
|
Work is in progress
|
Inspection Record Card- Fire | 12/22/2011 | | 12/22/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 12/22/2011 | | DONE |
|
|
|
t/c w matthew - permit ready and fees given
|
Permit Ready to Issue | | | 12/22/2011 | | DONE |
|
|
|
|
Issue and Print Permit | | | 12/22/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (Stephanie) | 12/13/2011 | | 12/21/2011 | | DONE |
Stephanie L. Cobbley
|
|
|
|
1st review completed | | | 12/21/2011 | | DONE |
|
|
|
|
Alarm Plan Check | 12/21/2011 | | 12/21/2011 | | PASS |
Stephanie L. Cobbley
|
|
|
Plans approved with redlines and review comments
|
PLANS TAKEN FRONT DESK ALARM | | | 12/21/2011 | | DONE |
|
|
|
Approved redlined plans available at front counter.
|
Application received | | | 12/13/2011 | | |
|
|
|
|