Permit Information
Permit NumberFIR11-00680
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 3550 W AMERICANA TERR
Project NameRIVERVIEW REHABILITATION
Customer NumberUDG ONLY
ePlanReviewNo
Description
The Fire Sprinkler Scope of work consists of approximately 6”x135’± C-900 underground piping with associated fittings and thrust blocks.


Building Department Scope:

BOISE SKILLED NURSING FACILITY - To construct a 25,100 sq. ft., single story, Type V-1hour, "I-2" Occupancy with "A-2 Dining and "B" occupancy Admin & Support Areas, Skilled Nursing Transitional Care Facility, restricted to 30 Beds in 30 Bedrooms as Private Suites. Patient occupant load is limited by certificate of occupancy and license by IDHW, W/ associated service areas, site work & parking. This building is fully sprinklered with alarm system based on occupancy use classification. Associated Dining Area (A2 occ.) is to be posted as Maximum Occupant Load "58". drs DRH10-00243; CUP10-00063
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  9/23/2013 DONE
DetailsTim Frost
Sent to Records for scanning.
INSP-Final Inspection2/6/20132/6/20132/6/2013APASS
DetailsForrest France
UG fire supply line permit okay to final.
FIR-Aging Inspection12/18/201212/18/201212/18/2012 DONE
DetailsForrest France
In progress
FIR-Aging Inspection9/13/20129/13/20129/14/2012 DONE
DetailsForrest France
Construction underway, site work in progress.
INSP-Sprinkler Rough-in/Hydro5/7/20125/7/20125/8/2012APART
DetailsForrest France
Scope of UG work to date approved.
INSP-Supply line flush4/17/20124/18/20124/19/2012APART
DetailsForrest France
UG fire supply line flush completed satisfactory.
INSP-Sprinkler Rough-in/Hydro2/29/20122/29/20122/29/2012PPASS
DetailsTim Frost
Underground hydro passed, no leakeage.
INSP-Sprinkler Rough-in/Hydro2/27/20122/28/20122/28/2012AFAIL
DetailsForrest France
UG fire supply line hydrostatic test failed due to visible leakage at the 1/2" valve and pressure loss at the guage.
INSP-Sprinkler Rough-in2/23/20122/23/20122/24/2012PPART
DetailsForrest France
UG fire supply line from the contractor point of connection to the IBR is approved for bury.
Plan assigned to (Tim)12/21/2011 12/22/2011 DONE
DetailsTim Frost
Sprinkler Plan Check12/22/2011 12/22/2011 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
1st review completed  12/22/2011 DONE
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  12/22/2011 DONE
DetailsTim Frost
Inspection Record Card- Fire12/22/2011 12/22/2011 DONE
DetailsPatricia Smith
Telephone call  12/22/2011 DONE
t/c w brad - permit ready and fees given
Permit Ready to Issue  12/22/2011 DONE
Details
Issue and Print Permit  12/22/2011 DONE
DetailsBarbara Stitt
Application received  12/21/2011