Miscellaneous action | | | 9/23/2013 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 2/6/2013 | 2/6/2013 | 2/6/2013 | A | PASS |
Forrest France
|
|
|
UG fire supply line permit okay to final.
|
FIR-Aging Inspection | 12/18/2012 | 12/18/2012 | 12/18/2012 | | DONE |
Forrest France
|
|
|
In progress
|
FIR-Aging Inspection | 9/13/2012 | 9/13/2012 | 9/14/2012 | | DONE |
Forrest France
|
|
|
Construction underway, site work in progress.
|
INSP-Sprinkler Rough-in/Hydro | 5/7/2012 | 5/7/2012 | 5/8/2012 | A | PART |
Forrest France
|
|
|
Scope of UG work to date approved.
|
INSP-Supply line flush | 4/17/2012 | 4/18/2012 | 4/19/2012 | A | PART |
Forrest France
|
|
|
UG fire supply line flush completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 2/29/2012 | 2/29/2012 | 2/29/2012 | P | PASS |
Tim Frost
|
|
|
Underground hydro passed, no leakeage.
|
INSP-Sprinkler Rough-in/Hydro | 2/27/2012 | 2/28/2012 | 2/28/2012 | A | FAIL |
Forrest France
|
|
|
UG fire supply line hydrostatic test failed due to visible leakage at the 1/2" valve and pressure loss at the guage.
|
INSP-Sprinkler Rough-in | 2/23/2012 | 2/23/2012 | 2/24/2012 | P | PART |
Forrest France
|
|
|
UG fire supply line from the contractor point of connection to the IBR is approved for bury.
|
Plan assigned to (Tim) | 12/21/2011 | | 12/22/2011 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 12/22/2011 | | 12/22/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 12/22/2011 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/22/2011 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 12/22/2011 | | 12/22/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 12/22/2011 | | DONE |
|
|
|
t/c w brad - permit ready and fees given
|
Permit Ready to Issue | | | 12/22/2011 | | DONE |
|
|
|
|
Issue and Print Permit | | | 12/22/2011 | | DONE |
Barbara Stitt
|
|
|
|
Application received | | | 12/21/2011 | | |
|
|
|
|