Miscellaneous action | | | 4/24/2012 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 3/7/2012 | 3/7/2012 | 3/7/2012 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 3/2/2012 | 3/5/2012 | 3/5/2012 | A | FAIL |
Troy Cobbley
|
|
|
The south most basement branchline has upright sprinkler heads that are blocked by beams that have been wrapped in sheet rock. It appears that by turning the branchlines and installing pendants that most of the problem will be fixed. Also on this same branchline the southwest end head is located too far from the wall but relocating it closer to the wall will fix this problem as long as 130 sq. ft. is not exceeded. I will need as-built drawings showing these changes prior to a final sign off.
|
INSP-Final Inspection | 3/1/2012 | 3/2/2012 | 3/2/2012 | A | DEFR |
Forrest France
|
|
|
Overbooked
|
Plan assigned to (Tim) | 2/28/2012 | | 2/29/2012 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 2/29/2012 | | 2/29/2012 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/29/2012 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 2/29/2012 | | 2/29/2012 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 2/29/2012 | | DONE |
|
|
|
t/c w brad - permit ready and fees given
|
Permit Ready to Issue | | | 2/29/2012 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 2/29/2012 | | DONE |
Christina Prado
|
|
|
|
Plan resubmittals received | | | 2/28/2012 | | DONE |
Tisha Gallop
|
|
|
PLAN MODIFICATION: Received three copies of applicaiton, submittal documents and plans; routed to Fire Review.
|
INSP-Final Inspection | 2/15/2012 | 2/16/2012 | 2/16/2012 | A | FAIL |
Troy Cobbley
|
|
|
Inspection was stopped after issues found with the pipe sizing on the plans as compared to what was installed/existing. This includes piping in the remote areas and out side of the remote areas. I also found additional elbows and risers nipples on one branchline. Plans need to be modified to show actual pipe sizing and fitting counts and submitted for review.
|
Plan assigned to (Tim) | 12/28/2011 | | 12/30/2011 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 12/30/2011 | | 12/30/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 12/30/2011 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/30/2011 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 12/30/2011 | | 12/30/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 12/30/2011 | | DONE |
|
|
|
t/c w brad - permit ready and fees given
|
Permit Ready to Issue | | | 12/30/2011 | | DONE |
|
|
|
|
Issue and Print Permit | | | 12/30/2011 | | |
|
|
|
|
Application received | | | 12/28/2011 | | |
|
|
|
|
Case Summary | | | 12/28/2011 | | DONE |
|
|
|
|