Permit Information
Permit NumberFIR12-00017
StatusFinaled
Name PHOENIX FIRE PROTECTION
Site Address 150 N CAPITOL BLVD
Project NameBoise City Hall
Customer Number 
ePlanReviewNo
Description
The Fire Sprinkler Scope of work consists of providing new fire protection for the southeast portion of the first floor. The SE portion of the first floor up to column line 2 will have quick response sprinklers. The existing area west of column 2 has standard response sprinklers. The system is supplied by an existing 250 Gpm @ 75 Psi fire pump located in the basement. The existing 4” main in the basement supplies the first floor system by a riser near the elevator. The new piping has 2” main and 1” branch lines. The system is tree type. A new floor control valve is to be provided.


Building Department Scope:

(BOISE CITY HALL)(PHASE 1) Seismic structural upgrades and tenant improvements to all 4 floors & basement of City Hall Building 1 in the City Hall Building complex per approved plans. Total area of four stories is approximately 179,881 sq. ft. with a 63,312 sq. ft. basement used as a parking garage and mechanical equipment & maintenance office area. Work to include select interior demolition; preparation for and installation of seismic ties, connectors, concrete footings, concrete walls, steel beams, steel columns, steel & concrete structural elements at floor infill of atrium at 2nd and 3rd floors, adding additional usable floor area; providing fire-resistive assemblies or applications of listed products to maintain the required fire-resistive construction for Type I-B Construction; opening up the first floor lobby and remodeling of the clerk's office area and service counter; new interior walls to create new conference rooms, future tenant areas and work areas with relocated or new millwork work stations; new interior finishes or repair in areas of remodel; new roof assembly to include foam plastic roof insulation and single ply TPO roof membrane as per specs; upgrade and or relocation of electrical, mechanical, plumbing, fire suppression and alarm systems.NOTE: This building complex is fully sprinklered. Drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  9/23/2013 DONE
DetailsTim Frost
Sent to Records for scanning.
INSP-Final Inspection6/14/20136/17/20136/17/2013APASS
DetailsForrest France
Final walkthrough completed. Scope of work finished, corrections done. Fire sprinkler permit finaled.
Plan assigned to (Tim)3/20/2013 3/22/2013 DONE
DetailsTim Frost
Sprinkler Plan Check3/22/2013 3/22/2013 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  3/22/2013 DONE
DetailsTim Frost
Telephone call  3/22/2013 DONE
DetailsChristina Prado
called phoenix Fire to advise permit is ready and gave fees due
Permit Ready to Issue  3/22/2013 DONE
DetailsChristina Prado
Inspection Record Card- Fire3/22/2013 3/22/2013 DONE
DetailsChristina Prado
(F) Reprint permit  3/22/2013 DONE
CHANGE STATUS TO (ISS)  3/22/2013  
Plan resubmittals received  3/20/2013 DONE
DetailsTisha Gallop
Plan Modification: Recieved three copies of application, submittal documents and plans; routed to Tim Frost.
INSP-Sprinkler Rough-in3/12/20133/13/20133/14/2013PPART
DetailsForrest France
Okay to cover drop ceilings at the 3rd and 4th floor north ends, and the sheetrock soffits at the 3rd floor elevator lobby. Upright coverage at the electrical room 3rd floor not yet installed.
FIR-Aging Inspection12/26/201212/26/201212/26/2012 DONE
DetailsForrest France
Site work in progress.
FIR-Aging Inspection9/24/20129/24/20129/28/2012 PEND
DetailsForrest France
In progress
INSP-Sprinkler Rough-in6/25/20126/27/20126/28/2012PPART
DetailsForrest France
See stamped plan set for areas marked/dated at the first floor lobby, reception, office and vestibule drop ceilings and soffits approved for cover.
FIR-Aging Inspection6/12/20126/12/20126/12/2012 PEND
DetailsForrest France
Construction underway. Need inspection request for work completed to date when ready.
Plan assigned to (Tim)1/18/2012 1/25/2012 DONE
DetailsTim Frost
Sprinkler Plan Check1/25/2012 1/25/2012 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
PLANS/APPL TAKEN TO FRONT DESK  1/25/2012 DONE
DetailsTim Frost
Inspection Record Card- Fire1/25/2012 1/25/2012 DONE
DetailsPatricia Smith
Telephone call  1/25/2012 DONE
t/c w don - permit ready and fees given
Permit Ready to Issue  1/25/2012 DONE
Details
Issue and Print Permit  1/25/2012 DONE
Sprinkler Plan Check1/20/2012 1/20/2012 FAIL
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
1st review completed  1/20/2012 FAIL
DetailsTim Frost
Miscellaneous action  1/20/2012 DONE
DetailsTim Frost
Emailed review to contractor
Telephone call  1/20/2012 DONE
DetailsBarbara Stitt
Called and told them p;ans were denied-need picked up and resubmitted on 1-19-12 @ 4:00PM//BAS
Application received  1/18/2012