Information based on query as of Thursday, July 4, 2024.
Permit Information
Permit NumberFIR12-00020
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 401 S BROADWAY AVE
Project NameWhole Foods Market
Customer NumberUDG ONLY
ePlanReviewNo
Description
The Fire Sprinkler Scope of work consists of 6” x 33’ C-900 underground piping with associated fittings, thrust blocks and restraints.


Building Department Scope:

Whole Foods Market (Cold Shell and Site Work Permit) - To construct a new 35,600 square foot, on story with 6,000 square foot mezzanine grocery store and related site improvements. The site work will include the entire site including the Walgreens. This building is constructed of masonry exterior walls and steel frame construction. This is a shell permit only and separate tenant improvement permit will be required to finish this building for occupancy. This building is fully fire sprinkled. The sprinklers are used for area increase. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  4/8/2013 DONE
DetailsTim Frost
Sent to Records for scanning.
INSP-Final Inspection10/29/201210/29/201210/29/2012PPASS
DetailsForrest France
Scope of work completed. Fire sprinkler permit finaled.
INSP-Supply line flush8/13/20128/14/20128/14/2012APART
DetailsForrest France
UG fire supply line flush completed.
INSP-Sprinkler Rough-in/Hydro6/14/20126/15/20126/15/2012APART
DetailsForrest France
UG fire supply line hydrostatic test completed satisfactory.
INSP-Sprinkler Rough-in5/31/20126/1/20126/1/2012APART
DetailsForrest France
UG fire supply line out 21' measured from the stem wall to the point of connection is approved for bury.
INSP-Sprinkler Rough-in3/9/20123/9/20123/9/2012PPART
DetailsForrest France
UG riser and stub out only.
INSP-Sprinkler Rough-in2/23/20122/24/20122/24/2012APART
DetailsForrest France
UG fire supply line IBR only approved for cover at this time.
Issue and Print Permit  1/24/2012 DONE
Plan assigned to (Tim)1/19/2012 1/23/2012 DONE
DetailsTim Frost
Sprinkler Plan Check1/23/2012 1/23/2012 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
1st review completed  1/23/2012 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  1/23/2012 DONE
DetailsTim Frost
Inspection Record Card- Fire1/23/2012 1/23/2012 DONE
DetailsPatricia Smith
Telephone call  1/23/2012 DONE
left vm for brad - permit ready and fees given
Permit Ready to Issue  1/23/2012 DONE
Details
Application received  1/19/2012