Miscellaneous action | | | 4/24/2012 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 3/29/2012 | 3/30/2012 | 3/30/2012 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 3/28/2012 | 3/29/2012 | 3/29/2012 | A | FAIL |
Troy Cobbley
|
|
|
Baffles have not been installed yet.
|
Sprinkler Plan Check | 3/27/2012 | | 3/27/2012 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/27/2012 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 3/27/2012 | | |
|
|
|
|
Inspection Record Card- Fire | 3/27/2012 | | 3/27/2012 | | DONE |
Darla L Downs
|
|
|
|
Telephone call | | | 3/27/2012 | | |
|
|
|
3-27-12 called Shilo permit ready and fee given ///dld
|
CHANGE STATUS TO (ISS) | | | 3/27/2012 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (Tim) | 3/20/2012 | | 3/27/2012 | | DONE |
Tim Frost
|
|
|
|
Plan resubmittals received | | | 3/26/2012 | | |
|
|
|
|
Sprinkler Plan Check | 3/21/2012 | | 3/21/2012 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
Miscellaneous action | | | 3/21/2012 | | DONE |
Tim Frost
|
|
|
Emailed review to contractor
|
Telephone call | | | 3/21/2012 | | DONE |
|
|
|
t/c w melody - permit denied - needs to be picked up and resubmitted
|
INSP-Sprinkler Rough-in/Hydro | 3/19/2012 | 3/20/2012 | 3/20/2012 | P | PASS |
Troy Cobbley
|
|
|
Hydro test passed. Waiting for the plan modifications to be approved to finish out permit
|
Plan resubmittals received | | | 3/20/2012 | | DONE |
Tisha Gallop
|
|
|
Plan Modificaiton: Received four copies of applciation, submittal docuements and plans; routed to Tim Frost.
|
INSP-Sprinkler Rough-in | 3/15/2012 | 3/15/2012 | 3/15/2012 | P | FAIL |
Troy Cobbley
|
|
|
Sprinkler heads are blocked by hvac roof penatrations/duct work in three locations. The head spacing shall meet NFPA 13 8.6.5.2.1.2 and 8.6.5.1.2. Unfortunatly some of this work is located in a remote hydraulic area. Also a soffit has been added at the main entry that was not shown on the plans. At this soffit the fitter added two additional heads. This now puts five heads on an 1 1/4" line where the remote area is flowing four heads off of 1 1/2" (1 1/4" branchline with 1 1/2" riser nipples). After speaking with Tim Frost it was determined that plan modifications will be needed prior to a final sign off showing all changes.
|
INSP-Sprinkler Rough-in | 2/22/2012 | 2/22/2012 | 2/22/2012 | P | PASS |
Troy Cobbley
|
|
|
Todays inspection covered the hangers and their attachment to the building structure. The fitter wants to use fencing nails to hold the all thread rods to the trusses thus elliminating the branchline seismic bracing. I defered him to plan review for a determination.
|
Issue and Print Permit | | | 2/13/2012 | | DONE |
|
|
|
|
(F) Reprint permit | | | 2/13/2012 | | DONE |
Barbara Stitt
|
|
|
|
(F) Reprint permit | | | 2/13/2012 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 2/7/2012 | | 2/8/2012 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 2/8/2012 | | 2/8/2012 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 2/8/2012 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/8/2012 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 2/8/2012 | | 2/8/2012 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 2/8/2012 | | DONE |
|
|
|
left message for cameron - permit ready and fees given
|
Permit Ready to Issue | | | 2/8/2012 | | DONE |
|
|
|
|
Application received | | | 2/7/2012 | | |
|
|
|
|