Miscellaneous action | | | 7/12/2012 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 5/30/2012 | 5/30/2012 | 5/30/2012 | P | PASS |
Forrest France
|
|
|
Final walkthrough passed. Contractor to provide stock of spare sprinklers of the new type installed at the head box as discussed. Permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 5/29/2012 | 5/29/2012 | 5/29/2012 | P | PASS |
Troy Cobbley
|
|
|
First floor dry system hydro test passed on the second try. Ken found and fixed the leak.
|
INSP-Sprinkler Rough-in/Hydro | 5/29/2012 | 5/29/2012 | 5/29/2012 | A | FAIL |
Troy Cobbley
|
|
|
Dry system hydro test failed due to visable drop of pressure on the guage. Rescheduled for this afternoon.
|
INSP-Sprinkler Rough-in | 5/15/2012 | 5/15/2012 | 5/15/2012 | P | PART |
Forrest France
|
|
|
OH rough-in partial.
|
INSP-Sprinkler Rough-in/Hydro | 5/11/2012 | 5/11/2012 | 5/11/2012 | A | PART |
Forrest France
|
|
|
OH hydrostatic testing 2nd thru 6th floors completed.
|
INSP-Sprinkler Rough-in/Hydro | 5/10/2012 | 5/10/2012 | 5/10/2012 | P | PART |
Forrest France
|
|
|
Hydrostatic testing for the 2nd floor system completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 5/9/2012 | 5/9/2012 | 5/9/2012 | P | PASS |
Troy Cobbley
|
|
|
Todays inspection was for multiple hydro tests on the 3rd, 4th, 5th and 6th floors. The hydro tests passed.
|
Plan assigned to (Tim) | 2/10/2012 | | 2/29/2012 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 2/29/2012 | | 2/29/2012 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/29/2012 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 2/29/2012 | | 2/29/2012 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 2/29/2012 | | DONE |
|
|
|
t/c w jeff - permit ready and fees given
|
Permit Ready to Issue | | | 2/29/2012 | | DONE |
|
|
|
|
Issue and Print Permit | | | 2/29/2012 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/28/2012 | | DONE |
Tisha Gallop
|
|
|
received three copies of application, submittal documents and plans; routed to Fire Reveiw
|
Sprinkler Plan Check | 2/15/2012 | | 2/15/2012 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 2/15/2012 | | FAIL |
|
|
|
|
Miscellaneous action | | | 2/15/2012 | | DONE |
Tim Frost
|
|
|
Sent contractor a copy of the review
|
Telephone call | | | 2/15/2012 | | DONE |
|
|
|
left vm for jeff - permit denied - needs to be picked up and resubmitted
|
Application received | | | 2/10/2012 | | |
|
|
|
|