INSP-Final Inspection | 10/24/2012 | 10/24/2012 | 10/30/2012 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Final Inspection | 10/22/2012 | 10/22/2012 | 10/30/2012 | P | PART |
Forrest France
|
|
|
Corrections finished, completed final walkthrough for the scope of permit work.
|
INSP-Final Inspection | 10/17/2012 | 10/19/2012 | 10/30/2012 | A | PART |
Forrest France
|
|
|
Plan modifications field verified to match installation and coverage adjustments.
|
Plan assigned to (Tim) | 7/25/2012 | | 8/1/2012 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 8/1/2012 | | 8/1/2012 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/1/2012 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 8/1/2012 | | DONE |
Barbara Stitt
|
|
|
|
Inspection Record Card- Fire | 8/1/2012 | | 8/1/2012 | | DONE |
Barbara Stitt
|
|
|
|
Issue and Print Permit | | | 8/1/2012 | | DONE |
Barbara Stitt
|
|
|
|
Plan resubmittals received | | | 7/25/2012 | | DONE |
Tisha Gallop
|
|
|
Plan Modification: received app and three copies of plans; routed to Fire Review.
|
INSP-Sprinkler Rough-in | 7/10/2012 | 7/10/2012 | 7/12/2012 | P | PART |
Forrest France
|
|
|
See inspection notes dated 7/11.
|
INSP-Sprinkler Rough-in | 7/10/2012 | 7/11/2012 | 7/11/2012 | P | PART |
Forrest France
|
|
|
Completed remainder of overhead rough-in at system #5. Heads at the upper level of the return plenum are not installed as indicated on approved plans. Seismic bracing and retainers are complete. Pendent head spacing at the north corridor adjusted to meet ft2 designed.
|
INSP-Sprinkler Rough-in/Hydro | 7/2/2012 | 7/3/2012 | 7/5/2012 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic test of system 5 completed.
|
INSP-Sprinkler Rough-in | 4/18/2012 | 4/19/2012 | 4/19/2012 | P | PART |
Forrest France
|
|
|
Completed initial rough-in inspection at the NE portion of system 5 including the 4" grid main and 2" branchlines to column line 11. Seismic bracing at the main is not yet installed, missing retainers at all 14" beams, BL at column C is incomplete, noted additional threaded couplings at several branchlines, need to maintain seismic clearance where piping passes through non-frangible construction.
|
Issue and Print Permit | | | 2/27/2012 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (Tim) | 2/23/2012 | | 2/24/2012 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 2/24/2012 | | 2/24/2012 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 2/24/2012 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/24/2012 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 2/24/2012 | | 2/24/2012 | | DONE |
Barbara Stitt
|
|
|
|
Permit Ready to Issue | | | 2/24/2012 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 2/24/2012 | | DONE |
Barbara Stitt
|
|
|
Emailed Paul that permit is ready & fees due on 2-24-12 @ 2:15pm//BAS
|
Application received | | | 2/23/2012 | | |
|
|
|
|