Miscellaneous action | | | 6/1/2012 | | DONE |
|
|
|
Plans taken to records for scanning.
|
INSP-Final Inspection | 5/9/2012 | 5/10/2012 | 5/10/2012 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 5/8/2012 | 5/9/2012 | 5/9/2012 | A | CANC |
Troy Cobbley
|
|
|
I was not contacted prior to the end of my work day that an inspection was wanted for tomorrow. Rescheduled for thursday morning.
|
INSP-Final Inspection | 5/7/2012 | 5/8/2012 | 5/8/2012 | A | FAIL |
Troy Cobbley
|
|
|
Simplex technician did not arrive at project site for inspection as scheduled. Noted seven over spaced strobes which were relocated by the electrician as Jason and I waited for Simplex. No functional testing of devices was performed.
|
Plan assigned to (Stephanie) | 3/23/2012 | | 4/10/2012 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Alarm Plan Check | 4/10/2012 | | 4/10/2012 | | PASS |
Stephanie L. Cobbley
|
|
|
Plan modification approved with redlines and review comments.
|
PLANS TAKEN FRONT DESK ALARM | | | 4/10/2012 | | DONE |
|
|
|
Approved redlined plans available at front counter.
|
Inspection Record Card- Fire | 4/10/2012 | | 4/10/2012 | | DONE |
Darla L Downs
|
|
|
|
Permit Ready to Issue | | | 4/10/2012 | | |
|
|
|
|
Telephone call | | | 4/10/2012 | | |
|
|
|
4-10-12 called Dante permit ready and fee given ///dld
|
Issue and Print Permit | | | 4/10/2012 | | DONE |
Tisha Gallop
|
|
|
|
Plan resubmittals received | | | 4/4/2012 | | DONE |
Christina Prado
|
|
|
Received two new sets of applications, checklists, plans and calcs. Documents given to Stephanie for additional review
|
Alarm Plan Check | 4/3/2012 | | 4/3/2012 | | FAIL |
Stephanie L. Cobbley
|
|
|
Plan modification denied - see redlines and review comments.
|
Miscellaneous action | | | 4/3/2012 | | DONE |
|
|
|
faxed SimplexGrinnell the review comments
|
Miscellaneous action | | | 4/3/2012 | | DONE |
|
|
|
Emailed Charlie Bayne at Simplexgrinnell to let him know the plans are being denied and that he can pick up the redlined plans at the permit counter.
|
Plan resubmittals received | | | 3/23/2012 | | DONE |
Christina Prado
|
|
|
PLAN MOD*** Received two new sets of plans, applications and checklists. Giving to Stephanie for review
|
Issue and Print Permit | | | 2/29/2012 | | DONE |
|
|
|
|
Application received | | | 2/28/2012 | | |
|
|
|
|
Plan assigned to (Stephanie) | 2/28/2012 | | 2/28/2012 | | DONE |
Scott Arellano
|
|
|
|
Plan assigned to (Stephanie) | 2/28/2012 | | 2/28/2012 | | PASS |
Stephanie L. Cobbley
|
|
|
Plans approved. Final approval will be subject to satisfactory field inspection by the PDS Fire inspector.
|
1st review completed | | | 2/28/2012 | | PASS |
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 2/28/2012 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/28/2012 | | 2/28/2012 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 2/28/2012 | | DONE |
|
|
|
left vm for dante - permit ready and fees given
|
Permit Ready to Issue | | | 2/28/2012 | | DONE |
|
|
|
|