Miscellaneous action | | | 10/11/2012 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 7/31/2012 | 7/31/2012 | 7/31/2012 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
Telephone call | | | 6/25/2012 | | DONE |
|
|
|
Spoke with Tony at Viking. Field changes required adding 6 additional ells. This increase the pressure requirment by approxiately 2.5#. The project still has a substantial safey factor.
|
INSP-Sprinkler Rough-in/Hydro | 6/19/2012 | 6/20/2012 | 6/20/2012 | P | PASS |
Troy Cobbley
|
|
|
24 hour air test passed for the pre-action system
|
INSP-Sprinkler Rough-in/Hydro | 6/19/2012 | 6/19/2012 | 6/19/2012 | P | PART |
Troy Cobbley
|
|
|
24 hour air test started at 1:30 with 44 psi on the guage.
|
INSP-Sprinkler Rough-in | 6/12/2012 | 6/13/2012 | 6/13/2012 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro tests on the dry and wet systems passed. Still need 24 hour air test on the dry. Rough-in for the sprinkler piping in the data room passed and the piping can be covered. The wet system piping rough-in passeed. Plan review needs to be contacted about modified hydraulic calculations due to the additional 2" elbows that have been added between the remote area and the supply.
|
Sprinkler Plan Check | 3/13/2012 | | 3/13/2012 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/13/2012 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 3/13/2012 | | 3/13/2012 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 3/13/2012 | | DONE |
|
|
|
t/c w tony - permit ready and fees given
|
Permit Ready to Issue | | | 3/13/2012 | | DONE |
|
|
|
|
Issue and Print Permit | | | 3/13/2012 | | |
|
|
|
|
Plan assigned to (Tim) | 2/29/2012 | | 3/13/2012 | | DONE |
Tim Frost
|
|
|
|
Telephone call | | | 3/8/2012 | | DONE |
|
|
|
Spoke with Tony Larson. Advised, him that I needed additional information from Drake plumbing. However, the person i need to talk with at Drake is out of the office until monday. Asked him if It was Ok to put his project on hold until Monday. He was aggreeable.
|
Telephone call | | | 3/8/2012 | | DONE |
|
|
|
Spoke with Drake Plumbing. The person I need to talk with is out of the office until Monday.
|
Plan resubmittals received | | | 3/7/2012 | | DONE |
Tisha Gallop
|
|
|
received three copies of application, submittal documents and plans; routed to Fire Review.
|
Sprinkler Plan Check | 3/5/2012 | | 3/5/2012 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 3/5/2012 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 3/5/2012 | | DONE |
Tim Frost
|
|
|
Emailed review to contractor
|
Telephone call | | | 3/5/2012 | | DONE |
|
|
|
left message with melissa - permit denied - needs to be picked up and resubmitted
|
Application received | | | 2/29/2012 | | |
|
|
|
|
Case Summary | | | 2/29/2012 | | DONE |
|
|
|
|