Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR12-00133
StatusFinaled
Name ALLIED GENERAL FIRE & SECURITY
Site Address 3358 N NORTH MOUNTAIN LN
Project Name3358 N NORTH MOUNTAIN LN
Customer Number 
ePlanReviewNo
Description
The Fire Sprinkler Scope of work consists of providing a wet pipe sprinkler system for a two level dwelling per NFPA 13D. All piping except for the riser will be CPVC.


Building Department Scope:

"This structure is located in Wildland Urban Interface zone A. Construction shall adhere to WUI construction standards." - To construct a new 6,492 square foot, One story w/ a daylight basement (3,689 square foot Main floor / 2,803 square foot Daylight basement) single family dwelling with 4 bedrooms, 5 bathrooms, two 1/2 baths, approximately 573 square feet of covered lower outdoor room, 770 square feet of main floor outdoor room, and a 2,228 square feet attached garage. All work shall be per the approved plans, Engineering, attached plan review report, and all other reviewing agencies approvals. This structure is located in WUI zone A and requires a class A fire-rated roofing material, noncombustible siding products and one hour fire rated soffits with no openings. A letter from the applicant’s geotechnical engineer indicating that the footing sub-grade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Terry Records at 384-3946. R-1B zoning, CFH10-00013, and setbacks per planning. A NFPA 13D sprinkler system is required and a Fire Sprinkler Permit is required prior to beginning any fire sprinkler work. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  10/11/2012 DONE
DetailsTim Frost
Sent to Records for scanning.
INSP-Final Inspection9/27/20129/27/20129/27/2012PPASS
DetailsTroy Cobbley
Permit finaled under FIR12-00405
FIR-Aging Inspection9/27/20129/27/20129/27/2012 PASS
DetailsTroy Cobbley
Permit finaled under FIR12-00405
INSP-Conference6/19/20126/19/20126/20/2012PDONE
DetailsForrest France
Jerry phone #: ###-#### or cell ###-####
INSP-Sprinkler Rough-in5/17/20125/21/20125/21/2012APART
DetailsForrest France
Insulation tenting for cold cavity protection at the main level completed okay with the exception of four locations. General and sub-contractor finished adjustments today while on site. Overhead install approved for cover. Also discussed obstruction criteria with regard to residential style heads such as light fixtures, finishes, etc.
INSP-Sprinkler Rough-in5/16/20125/17/20125/17/2012ACANC
DetailsTroy Cobbley
Cancel per bruce. Insulation is not yet complete will call for re-inspection next week.
INSP-Sprinkler Rough-in5/9/20125/9/20125/9/2012APART
DetailsForrest France
Main level insulation and cover at walls only approved at this time.
INSP-Sprinkler Rough-in/Hydro5/7/20125/7/20125/8/2012APART
DetailsForrest France
Main level cover approval pending completion of tenting.
INSP-Sprinkler Rough-in5/3/20125/3/20125/4/2012PPART
DetailsForrest France
Verified plan modification work. Basement rough-in only okayed for cover. Discussed cold cavity protection issues at the first floor and underground fire supply line work that appears to have been completed without an associated FIR permit or inspection for cover.
CHANGE STATUS TO (ISS)  5/3/2012 DONE
DetailsChristina Prado
Plan assigned to (Tim)4/27/2012 5/1/2012 DONE
DetailsTim Frost
Sprinkler Plan Check5/1/2012 5/1/2012 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
PLANS/APPL TAKEN TO FRONT DESK  5/1/2012 DONE
DetailsTim Frost
Inspection Record Card- Fire5/1/2012 5/1/2012 DONE
DetailsDarla L Downs
Permit Ready to Issue  5/1/2012  
Telephone call  5/1/2012  
5-1-12 called Allied General Fire permit ready and fee given ///dld
Plan resubmittals received  4/27/2012 DONE
DetailsTisha Gallop
Plan Modification: Received three copies of appliation, submittal documents and plans; routed to Tim Frost.
INSP-Sprinkler Rough-in4/18/20124/19/20124/19/2012AFAIL
DetailsTroy Cobbley
The piping installation does not match the approved plans. The riser location has been changed. Pipe routing for the main and branchlines has changed. Pipe routing to and in the basement remote area has changed. Pendant head locations have changed. Pendants are supplied from different sources. Alot of additional fittings have been added including four additional elbows in the basement remote area. This does not include the additional fittigns in the supply piping to the remote area. Pendants have been relocated to soffits instead of being installed in the high ceiling areas. Also the wall layout does not match in all locations to the city approved plans. There are areas where hvac duct work is obstructing the pendant heads. Todays inspection was only for the basement area since the main level piping has not been completed yet. Plans need to be resubmitted showing all changes in routing and fitting counts prior to covering by sheet rock. I spoke to Bruce the fitter, Tony Young and with Jerry with Petra about the issues but agreed that I would allow the installation of insulation, for sound proofing, above the piping. This insulation, it was agreed would be installed above the sprinkler piping and would not obstruct my view of the sprinkler piping for the future cover inspection.
Issue and Print Permit  4/3/2012 DONE
Plan assigned to (Tim)3/8/2012 3/20/2012 DONE
DetailsTim Frost
Sprinkler Plan Check3/20/2012 3/20/2012 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
PLANS/APPL TAKEN TO FRONT DESK  3/20/2012 DONE
DetailsTim Frost
Inspection Record Card- Fire3/20/2012 3/20/2012 DONE
DetailsPatricia Smith
Telephone call  3/20/2012 DONE
left vm for bill - permit ready and fees given
Permit Ready to Issue  3/20/2012 DONE
Details
Plan resubmittals received  3/15/2012  
3-15-12 Received 3 applications & plans sent to Tim F.
Sprinkler Plan Check3/12/2012 3/12/2012 FAIL
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
1st review completed  3/12/2012 FAIL
DetailsTim Frost
Miscellaneous action  3/12/2012 DONE
DetailsTim Frost
Emailed review to contractor
Telephone call  3/12/2012 DONE
t/c w bill - permit denied - needs to be picked up and resubmitted
Application received  3/8/2012