Miscellaneous action | | | 4/8/2013 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 11/19/2012 | 11/20/2012 | 11/20/2012 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 11/8/2012 | 11/8/2012 | 11/8/2012 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given until the fire sprinkler corrections have been addressed.
|
INSP-Sprinkler Rough-in | 9/27/2012 | 9/27/2012 | 9/27/2012 | P | PART |
Troy Cobbley
|
|
|
Sprinkler rough-in is passed but the sprinkler heads in the corridor as shown on the plans are to be large orfice but as installed are not. I spoke to Jim and he is going to address this issue with Tim Frost.
|
FIR-Aging Inspection | 9/27/2012 | 9/27/2012 | 9/27/2012 | | PASS |
Troy Cobbley
|
|
|
Rough-in inspection scheduled
|
Override - Parcel Holds | 5/3/2012 | 1/1/1900 | 5/3/2012 | | |
|
|
|
not to do with plan mod
|
Issue and Print Permit | | | 4/12/2012 | | DONE |
Barbara Stitt
|
|
|
|
Miscellaneous action | | | 4/11/2012 | | DONE |
|
|
|
Received the missing documentation today so that I can process this permit.
|
Sprinkler Plan Check | 4/11/2012 | | 4/11/2012 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/11/2012 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 4/11/2012 | | 4/11/2012 | | DONE |
Darla L Downs
|
|
|
|
Permit Ready to Issue | | | 4/11/2012 | | |
|
|
|
|
Telephone call | | | 4/11/2012 | | |
|
|
|
4-11-12 called permit ready and fee given ///dld
|
Plan assigned to (Tim) | 3/30/2012 | | 4/11/2012 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 4/5/2012 | | DONE |
Tisha Gallop
|
|
|
contractor picked up denied plans
|
Plan resubmittals received | | | 4/5/2012 | | DONE |
Tisha Gallop
|
|
|
received three copies of applications, sumittal docs and plans; routed to Fire Review.
|
Sprinkler Plan Check | 4/4/2012 | | 4/4/2012 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 4/4/2012 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 4/4/2012 | | DONE |
Tim Frost
|
|
|
Emailed review to contractor
|
Application received | | | 3/30/2012 | | |
|
|
|
|
Case Summary | | | 3/30/2012 | | DONE |
Barbara Stitt
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 5/3/2012 | 5/4/2012 | | A | |
Tim Frost
|
|
|
Partial, Ok to cover. Indicated in blue on plans which areas. Passed hydro for mezz
|