Permit Information
Permit NumberFIR12-00223
StatusFinaled
Name AMERICAN FIRE PROTECTION LLC
Site Address 1253 N COLE RD
Project NamePEACE IN JESUS LUTHERAN CHURCH
Customer Number 
ePlanReviewNo
Description
Plan Mod #1 7/09/2012
Based on actual field conditions; the secondary main was 1¼” instead of 1½” that was originally shown. New hydraulic calculations were submitted and are adequate.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  10/11/2012 DONE
DetailsTim Frost
Sent to Records for scanning.
INSP-Final Inspection8/1/20128/3/20128/3/2012APASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection7/31/20128/1/20128/1/2012PCANC
DetailsTroy Cobbley
Cancel per Jeff since the project related fire alarm permit has not been scheduled.
INSP-Final Inspection7/30/20127/31/20127/31/2012ACANC
DetailsTroy Cobbley
Canceled per Jeff Phone #: ###-####. Fire alarm contractor is not there.
Issue and Print Permit  7/10/2012 DONE
Plan assigned to (Tim)7/6/2012 7/9/2012 DONE
DetailsTim Frost
Sprinkler Plan Check7/9/2012 7/9/2012 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
PLANS/APPL TAKEN TO FRONT DESK  7/9/2012 DONE
DetailsTim Frost
Inspection Record Card- Fire7/9/2012 7/9/2012 DONE
DetailsDarla L Downs
Permit Ready to Issue  7/9/2012  
Telephone call  7/9/2012  
7-9-12 called American Fire Protection -permit ready and fee given ///dld
Plan resubmittals received  7/6/2012 DONE
DetailsTisha Gallop
Plan Modification: Received three copies of application, submittal documents and plans; routed to fire reveiw.
INSP-Sprinkler Rough-in/Hydro7/2/20127/2/20127/2/2012PPART
DetailsTroy Cobbley
Hydro test passed. Sprinkler piping above the lay-in ceiling tile is ok to cover. Plans and hydraulic calculations need to be resubmitted showing the 1 1/4" far main. The plans and calculations show the piping as 1 1/2" piping. Need the pressure relief valve installed.
INSP-Sprinkler Rough-in/Hydro6/4/20126/5/20126/5/2012PPASS
DetailsTroy Cobbley
The overhead hydro test and rough-in of the north canopy dry system passed. The earth quake bracing on the main has not been installed yet.
INSP-Sprinkler Rough-in6/5/20126/5/20126/5/2012PPASS
DetailsTroy Cobbley
This entry is for an inspection called in under FIR12-00175 on 5/17/2012.

The overhead hydro test passed. The sprinkler piping in the Sanctuary/Fellowship areas is ok to cover.
Issue and Print Permit  5/17/2012 DONE
Plan assigned to (Tim)5/4/2012 5/7/2012 DONE
DetailsTim Frost
Sprinkler Plan Check5/7/2012 5/7/2012 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
PLANS/APPL TAKEN TO FRONT DESK  5/7/2012 DONE
DetailsTim Frost
Inspection Record Card- Fire5/7/2012 5/7/2012 DONE
DetailsDarla L Downs
Permit Ready to Issue  5/7/2012  
Telephone call  5/7/2012  
5-7-12 called American Fire Protection permit ready and fee given ///dld
Plan assigned to (Tim)5/1/2012 5/7/2012 DONE
DetailsTim Frost
Plan assigned to (Tim)5/2/2012 5/7/2012 DONE
DetailsTim Frost
put in ready mode by mistake ///dld
Plan resubmittals received  5/4/2012 DONE
DetailsChristina Prado
Received three sets of applications; checklists; Idaho Power Document; Calcs and plans marked FP1 of 1. Given to Tim Frost for review
Sprinkler Plan Check5/2/2012 5/2/2012 FAIL
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
1st review completed  5/2/2012 FAIL
DetailsTim Frost
Miscellaneous action  5/2/2012 DONE
DetailsTim Frost
Emailed review to contractor
Application received  5/1/2012  
Case Summary  5/1/2012 DONE
DetailsAlexandra L. DeYoung