Miscellaneous action | | | 7/12/2012 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 6/11/2012 | 6/11/2012 | 6/11/2012 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 5/29/2012 | 5/29/2012 | 5/29/2012 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed.
|
INSP-Sprinkler Rough-in | 5/14/2012 | 5/14/2012 | 5/14/2012 | P | PASS |
Troy Cobbley
|
|
|
The sprinkler piping above the hardlids is ok for cover. Myself, Jeremy and the job superintendant discussed possible sprinklers being blocked by fixtures/valances. Jeremy is going to investigate. Another rough-in inspection will be required when the T-bar is installed. Upright sprinkler coverage will be required in the stock room. Bracing will be required for sprig ups over 4'.
|
Permit Ready to Issue | | | 5/7/2012 | | DONE |
Barbara Stitt
|
|
|
|
Issue and Print Permit | | | 5/7/2012 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (Tim) | 5/1/2012 | | 5/4/2012 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 5/4/2012 | | 5/4/2012 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/4/2012 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 5/4/2012 | | 5/4/2012 | | DONE |
Darla L Downs
|
|
|
|
Permit Ready to Issue | | | 5/4/2012 | | |
|
|
|
|
Telephone call | | | 5/4/2012 | | |
|
|
|
5-4-12 called Treasure Valley Fire (RON) permit ready and fee given /// dld
|
Sprinkler Plan Check | 5/3/2012 | | 5/3/2012 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 5/3/2012 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 5/3/2012 | | DONE |
Tim Frost
|
|
|
Emailed review to contractor
|
Telephone call | | | 5/3/2012 | | |
|
|
|
5-3-12 called Brodie for pick up ///dld
|
Plan resubmittals received | | | 5/3/2012 | | DONE |
Alexandra L. DeYoung
|
|
|
rec'd 3 apps and plans
|
Application received | | | 5/1/2012 | | |
|
|
|
|