Miscellaneous action | | | 9/23/2013 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 4/25/2013 | 4/25/2013 | 4/25/2013 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
FIR-Aging Inspection | 3/14/2013 | 3/14/2013 | 3/15/2013 | | NR |
Troy Cobbley
|
|
|
work is in progress
|
INSP-Sprinkler Rough-in | 12/4/2012 | 12/4/2012 | 12/4/2012 | P | PASS |
Troy Cobbley
|
|
|
flush for bldgs 5, 6 & 7 - passed inspection
|
INSP-Supply line flush | 10/30/2012 | 10/31/2012 | 10/31/2012 | A | PASS |
Troy Cobbley
|
|
|
Underground flush of buildings 8 and 10 passed
|
INSP-Sprinkler Rough-in | 10/30/2012 | 10/31/2012 | 10/31/2012 | A | CANC |
Troy Cobbley
|
|
|
Underground fluch - Jonathan Phone #: ###-####///scheduled wrong type
|
Plan resubmittals received | | | 10/29/2012 | | |
|
|
|
rec'd 3 copies of fp-1
|
INSP-Supply line flush | 9/25/2012 | 9/25/2012 | 9/25/2012 | P | PASS |
Troy Cobbley
|
|
|
blg 9, Underground supply line flush passed
|
INSP-Supply line flush | 9/24/2012 | 9/25/2012 | 9/25/2012 | A | PASS |
Troy Cobbley
|
|
|
blg 11,underground supply line flush passed
|
Telephone call | | | 9/24/2012 | | DONE |
|
|
|
Spoke with contractor. He said it would be nessecary to install a tee after the underground for testing due to United Water requirments. I said it would be required to be monitored unless it was permanently capped to prevent water flowing.
|
INSP-Sprinkler Rough-in | 9/6/2012 | 9/7/2012 | 9/7/2012 | A | PASS |
Troy Cobbley
|
|
|
Underground hydro tests for BLD 5, 6 & 7 passed.
|
INSP-Sprinkler Rough-in | 8/30/2012 | 8/31/2012 | 8/31/2012 | A | PART |
Forrest France
|
|
|
UG fire supply lines including the IBR's at buildings 5, 6, and 7 are approved for bury- see clouded annotations with today's date on stamped plan set. Note* supply pipe route changes matching field modifications are included on the overhead plan set.
|
INSP-Sprinkler Rough-in/Hydro | 8/16/2012 | 8/17/2012 | 8/17/2012 | A | PART |
Forrest France
|
|
|
UG fire supply line hydrostatic test for building 10 passed.
|
INSP-Sprinkler Rough-in | 8/15/2012 | 8/16/2012 | 8/16/2012 | A | PASS |
Troy Cobbley
|
|
|
The underground hydro for Bld 8 passed
|
INSP-Sprinkler Rough-in | 8/15/2012 | 8/16/2012 | 8/16/2012 | A | PASS |
Troy Cobbley
|
|
|
The underground cover for bld 10 passed.
|
INSP-Sprinkler Rough-in | 8/15/2012 | 8/15/2012 | 8/15/2012 | P | CANC |
Troy Cobbley
|
|
|
Concrete for thrust blocks not available. To be canceled per johnathan- this is for underground cover bld 10 Phone #: ###-####
|
INSP-Sprinkler Rough-in | 8/3/2012 | 8/3/2012 | 8/6/2012 | P | PASS |
Troy Cobbley
|
|
|
Jonathan underground supply cover for bld 8 is ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 8/3/2012 | 8/3/2012 | 8/3/2012 | P | PASS |
Troy Cobbley
|
|
|
Hydro test bld 11 on underground supply passed.
|
INSP-Sprinkler Rough-in | 8/2/2012 | 8/3/2012 | 8/3/2012 | P | PASS |
Troy Cobbley
|
|
|
Hydro test of bld 9 underground passed.
|
INSP-Sprinkler Rough-in | 7/30/2012 | 7/30/2012 | 7/30/2012 | P | PASS |
Troy Cobbley
|
|
|
The underground cover inspection for bld 10 passed.
|
INSP-Sprinkler Rough-in | 7/26/2012 | 7/27/2012 | 7/27/2012 | A | PART |
Forrest France
|
|
|
UG fire supply line cover at buildings 9 and 11 approved for bury. Modifications to the original design are included in the new overhead plans.
|
INSP-Sprinkler Rough-in | 7/25/2012 | 7/26/2012 | 7/27/2012 | P | PART |
Forrest France
|
|
|
Field changes in UG fire supply line routing for buildings 9 and 11 field verified and approved- see dated and initialed notes on the stamped plan set.
|
INSP-Sprinkler Rough-in | 6/1/2012 | 6/4/2012 | 6/4/2012 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the locations at four buildings where a partial approval has been given to cover the underground supply piping. Locations are marked in red with approximate pipe lengths.
|
Issue and Print Permit | | | 6/1/2012 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 5/23/2012 | | 5/24/2012 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/24/2012 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 5/24/2012 | | 5/24/2012 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
Inspection Record Card- Fire | 5/24/2012 | | 5/24/2012 | | DONE |
Darla L Downs
|
|
|
|
Permit Ready to Issue | | | 5/24/2012 | | |
|
|
|
|
Telephone call | | | 5/24/2012 | | |
|
|
|
5-24-12 called JBL Fire left message permit ready and fee given ///dld
|
Plan resubmittals received | | | 5/23/2012 | | DONE |
Christina Prado
|
|
|
Received three copies of correction letter and three sets of plans marked FP-1. Routed to Tim Frost for additional review
|
Plan assigned to (Tim) | 5/15/2012 | | 5/16/2012 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 5/16/2012 | | 5/16/2012 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 5/16/2012 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 5/16/2012 | | DONE |
Tim Frost
|
|
|
Emailed review to contractor
|
Telephone call | | | 5/16/2012 | | |
|
|
|
5-16-12 called JBL Fire Protection left message permit ready for pick up ///dld
|
Application received | | | 5/15/2012 | | |
|
|
|
|