Miscellaneous action | | | 10/11/2012 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 9/19/2012 | 9/19/2012 | 9/20/2012 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled. Forward flow completed with two outlets (3"@755/ 2.5"@694).
|
INSP-Final Inspection | 9/12/2012 | 9/13/2012 | 9/13/2012 | P | NR |
Forrest France
|
|
|
Foward flow test did not meet system design.
|
INSP-Sprinkler Rough-in/Hydro | 8/7/2012 | 8/7/2012 | 8/27/2012 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic test completed satisfactory.
|
INSP-Sprinkler Rough-in | 8/9/2012 | 8/9/2012 | 8/9/2012 | A | PART |
Forrest France
|
|
|
Okay to cover grid ceilings at the second floor offices, storage, hall and stairway areas.
|
INSP-Sprinkler Rough-in | 8/3/2012 | 8/6/2012 | 8/8/2012 | A | PART |
Forrest France
|
|
|
Overhead rough-in at the hanger area passed.
|
INSP-Sprinkler Rough-in | 7/10/2012 | 7/10/2012 | 7/10/2012 | P | PART |
Forrest France
|
|
|
Completed rough-in inspection for the lower office area only. Note* work appears satisfactory however plans do not match installation- cover approval is conditional upon plan resubmittals.
|
Issue and Print Permit | | | 7/5/2012 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 6/7/2012 | | 7/3/2012 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 7/3/2012 | | 7/3/2012 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/3/2012 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 7/3/2012 | | 7/3/2012 | | DONE |
Darla L Downs
|
|
|
|
Permit Ready to Issue | | | 7/3/2012 | | |
|
|
|
|
Telephone call | | | 7/3/2012 | | |
|
|
|
7-3-12 called Jeff- Treasure Valley Fire permit ready and fee given///dld
|
Plan resubmittals received | | | 6/28/2012 | | DONE |
Christina Prado
|
|
|
received three new sets of applications; checklists; plans FP-1 & FP-2; response letters and calcs. Gave to Tim Frost for further review
|
Sprinkler Plan Check | 6/15/2012 | | 6/15/2012 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 6/15/2012 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 6/15/2012 | | DONE |
Tim Frost
|
|
|
Emailed review to contractor
|
Telephone call | | | 6/15/2012 | | DONE |
|
|
|
can come pick up denied plans
|
Application received | | | 6/7/2012 | | |
|
|
|
|