Miscellaneous action | | | 4/8/2013 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 11/29/2012 | 11/29/2012 | 11/29/2012 | P | PASS |
Forrest France
|
|
|
Final walkthrough and inspection completed. Forward flow passed. Fire sprinkler permit finaled.
|
INSP-Final Inspection | 11/28/2012 | 11/28/2012 | 11/29/2012 | P | NR |
Forrest France
|
|
|
Final pending project related fire alarm testing for riser supervision. Also need to complete forward flow test.
|
INSP-Sprinkler Rough-in/Hydro | 11/28/2012 | 11/28/2012 | 11/29/2012 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic test completed satisfactory. Need to add baffles per approved plan.
|
INSP-Sprinkler Rough-in | 11/13/2012 | 11/14/2012 | 11/14/2012 | A | PART |
Forrest France
|
|
|
Existing storeroom and stock area fire sprinkler work passed overhead rough-in inspection. Okayed for ceiling cover- see plans for dated annotations.
|
INSP-Sprinkler Rough-in | 11/8/2012 | 11/13/2012 | 11/13/2012 | A | CANC |
Troy Cobbley
|
|
|
Cancel per mike Phone #: ###-####
|
INSP-Sprinkler Rough-in | 10/29/2012 | 10/30/2012 | 10/31/2012 | P | PART |
Forrest France
|
|
|
Overhead rough-in at the upper warehouse passed- see plans for dated annotations.
|
Sprinkler Plan Check | 10/16/2012 | | 10/16/2012 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/16/2012 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 10/16/2012 | | 10/16/2012 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/16/2012 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 10/16/2012 | | 10/16/2012 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 10/16/2012 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 10/16/2012 | | DONE |
Tisha Gallop
|
|
|
called Brodie and left vm permit is ready and fee.
|
Issue and Print Permit | | | 10/16/2012 | | DONE |
Tisha Gallop
|
|
|
|
Plan resubmittals received | | | 10/11/2012 | | DONE |
|
|
|
rec'd three sets
|
Sprinkler Plan Check | 9/11/2012 | | 9/11/2012 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
Telephone call | | | 9/11/2012 | | DONE |
Christina Prado
|
|
|
called to advise resubmittals are needed for approval
|
Plan resubmittals received | | | 9/6/2012 | | DONE |
Christina Prado
|
|
|
Received three reviced sets of drawings, calcs, applications and checklists. Gave to Tim frost for further review
|
Early Start | | | 8/15/2012 | | PASS |
|
|
|
Please, see attached approved Early Start Request.
|
Plan assigned to (Tim) | 6/19/2012 | | 8/13/2012 | | DONE |
Tim Frost
|
|
|
|
Telephone call | | | 7/11/2012 | | DONE |
|
|
|
Recevied the high pile storage form and the owner's certificate today 07-11-12. Both forms confirmed that they have storage 16' high with solid shelving.
I called TVFP (Brodie) and told them that all comments in my review remain as is; nothing has changed.
|
Sprinkler Plan Check | 6/25/2012 | | 6/25/2012 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 6/25/2012 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 6/25/2012 | | DONE |
Tim Frost
|
|
|
Emailed review to contractor
|
Telephone call | | | 6/25/2012 | | |
|
|
|
6-25-12 called Brodie Treasure Valley Fire permit ready for pick up///dld
|
Application received | | | 6/19/2012 | | |
|
|
|
|
Case Summary | | | 6/19/2012 | | DONE |
Barbara Stitt
|
|
|
|