Miscellaneous action | | | 10/11/2012 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 9/20/2012 | 9/21/2012 | 9/21/2012 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. The stairs have not been installed but as described by the general contractor the pendant heads around this area will provide adequate coverage.
|
INSP-Supply line flush | 7/30/2012 | 7/31/2012 | 7/31/2012 | A | PART |
Forrest France
|
|
|
UG fire supply line flush completed.
|
INSP-Sprinkler Rough-in/Hydro | 7/18/2012 | 7/20/2012 | 7/20/2012 | A | PASS |
Tim Frost
|
|
|
Passed rough in and udg hydro.
|
INSP-Sprinkler Rough-in | 7/16/2012 | 7/17/2012 | 7/17/2012 | A | PART |
Forrest France
|
|
|
Additional fittings and changes in pipe routing for the underground supply line verified with plan review as within calcs. Verified corrections for bedding, okayed for bury.
|
INSP-Supply line flush | 7/13/2012 | 7/16/2012 | 7/16/2012 | A | FAIL |
Forrest France
|
|
|
Field installation does not match approved plans. The water meter appears to be upstream of the point of connection, line size does not correlate, noted ten additional fitting- 6 (90's) 4 (45's) in the supply line. Need to resubmit plans and calculations supporting field modifications. Also noted insufficient pipe support due to large gaps and voids in the trench. Backfill methods to meet NFPA 13 10.9.1, 10.9.2.
|
INSP-Sprinkler Rough-in | 7/12/2012 | 7/13/2012 | 7/13/2012 | A | FAIL |
Troy Cobbley
|
|
|
Inspection was for the underground supply. No approved plans on site for inspection. I did note that the vertical rise of the underground supply needs to rise up under the house not under the footing. Also per my conversation with the fitter additional fittings had to be installed to pipe the underground. Also the underground supply piping, when it enters the crawl space, can not lay on the dirt. It must be attached directly to the bottom of the floor joists. It also appears that the underground supply may be utilizing a water meter. I spoke to Tom in Shilo's office of these issues.
|
INSP-Sprinkler Rough-in | 7/10/2012 | 7/12/2012 | 7/12/2012 | P | NR |
Forrest France
|
|
|
This is an ug to cover. Richard is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 7/10/2012 | 7/11/2012 | 7/10/2012 | A | CANC |
Forrest France
|
|
|
This is an ug to cover. Richard is the contact. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
Issue and Print Permit | | | 7/10/2012 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 6/26/2012 | | 7/9/2012 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 7/9/2012 | | 7/9/2012 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/9/2012 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 7/9/2012 | | 7/9/2012 | | DONE |
Darla L Downs
|
|
|
|
Permit Ready to Issue | | | 7/9/2012 | | |
|
|
|
|
Telephone call | | | 7/9/2012 | | |
|
|
|
7-9-12 called Shilo Automatic Sprinkler-permit ready and fee given///dld
|
Plan resubmittals received | | | 7/2/2012 | | DONE |
Tisha Gallop
|
|
|
received three copies of application, submittal documents and plans; routed to Fire Review.
|
Sprinkler Plan Check | 6/29/2012 | | 6/29/2012 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 6/29/2012 | | FAIL |
|
|
|
|
Telephone call | | | 6/29/2012 | | |
|
|
|
6-29-12 called Shilo Automatic Sprinkler permit ready for pick up///dld
|
Application received | | | 6/26/2012 | | |
|
|
|
|