Information based on query as of Friday, June 28, 2024.
Permit Information
Permit NumberFIR12-00347
StatusFinaled
Name ABSOLUTE FIRE PROTECTION
Site Address 4515 N GLENWOOD ST
Project NameHilltop Inter Care Facility
Customer Number 
ePlanReviewNo
Description
The fire sprinkler scope of work consists of changing an existing single family dwelling into residential care assisted living facility. The NFPA 13R system is supplied by a dedicated 2” underground. The riser is 1¼” and has a 1½” fire department connection. The system has 1¼” mains with 1” lines.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  10/11/2012 DONE
DetailsTim Frost
Sent to Records for scanning.
INSP-Final Inspection8/16/20128/17/20128/17/2012APASS
DetailsForrest France
Correction items verified for completion. Fire sprinkler permit finaled.
INSP-Final Inspection8/16/20128/16/20128/16/2012PCANC
DetailsTroy Cobbley
Overbooked. Left voice message for Sam about rescheduling.
INSP-Final Inspection8/15/20128/16/20128/16/2012ACANC
DetailsTroy Cobbley
Call 30 minutes prior to arrival Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
INSP-Final Inspection8/14/20128/15/20128/15/2012AFAIL
DetailsTroy Cobbley
Provide tamper switches, backflow certification, riser tags and add sprinkler protection in the riser room due to the wall that was built.
INSP-Final Inspection8/13/20128/14/20128/14/2012AFAIL
DetailsTroy Cobbley
Underground flush passed. Can't final until the interconnections with the fire alarm system have been verified.
INSP-Final Inspection8/10/20128/13/20128/13/2012AFAIL
DetailsTroy Cobbley
The underground water supply has been turned off so no testing can be completed.
INSP-Sprinkler Rough-in/Hydro8/8/20128/8/20128/8/2012PPART
DetailsTroy Cobbley
Underground hydro test passed.
INSP-Supply line flush8/6/20128/7/20128/7/2012APART
DetailsTroy Cobbley
The underground flush failed but the overhead hydro test passed. As per discussion the underground supply line needs to be hydro tested at static plus 50psi for two hours.
Plan assigned to (Tim)8/1/2012 8/3/2012 DONE
DetailsTim Frost
Sprinkler Plan Check8/3/2012 8/3/2012 PASS
DetailsTim Frost
Reviewed as built changes. Ok
PLANS/APPL TAKEN TO FRONT DESK  8/3/2012 DONE
DetailsTim Frost
Inspection Record Card- Fire8/3/2012 8/3/2012 DONE
DetailsDarla L Downs
Permit Ready to Issue  8/3/2012  
Telephone call  8/3/2012  
8-3-12 called Absolute Fire - permit ready for pick up ///dld
Issue and Print Permit  8/3/2012 DONE
Plan resubmittals received  8/1/2012 DONE
DetailsChristina Prado
Received three new sets of plans, applications, checklists, fire flow sheet and calcs. Gave to Tim for review
INSP-Supply line flush7/31/20127/31/20127/31/2012APART
DetailsTroy Cobbley
Todays inspection was actually a cover inspection for the underground supply and a overhead rough-in. The underground supply can be buried and for the most part the rough-in is passed. Except for one head as marked on the plans is overspaced and plans need to be resubmitted addressing the additional fitting in the piping to the remote area. The new fittings appear to be due to pipe routing changes.
Issue and Print Permit  7/11/2012 DONE
Plan assigned to (Tim)7/2/2012 7/6/2012 DONE
DetailsTim Frost
Sprinkler Plan Check7/6/2012 7/6/2012 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
1st review completed  7/6/2012 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  7/6/2012 DONE
DetailsTim Frost
Inspection Record Card- Fire7/6/2012 7/6/2012 DONE
DetailsDarla L Downs
Permit Ready to Issue  7/6/2012  
Telephone call  7/6/2012  
7-6-12 called Sam- Absolute Fire permit ready and fee given ///dld
Application received  7/2/2012