INSP-Final Inspection | 9/18/2012 | 9/19/2012 | 9/19/2012 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit work approved for final status.
|
INSP-Sprinkler Rough-in/Hydro | 9/17/2012 | 9/17/2012 | 9/17/2012 | P | PASS |
Forrest France
|
|
|
Rough-in work finished and passed inspection. Previous correction items are complete.
|
INSP-Sprinkler Rough-in | 8/28/2012 | 8/28/2012 | 8/28/2012 | P | PART |
Troy Cobbley
|
|
|
There are three rooms that the walls to go to the deck to provide an enclosed area to operate the provided upright sprinkler or provide a ceiling with a pendant sprinkler or the final option is to meet coverage as provided in NFPA 13 chapter 8. I also found one pendant head located 4" too far from a wall. Piping can be covered except for the problem areas.
|
Issue and Print Permit | | | 7/23/2012 | | DONE |
|
|
|
|
Application received | | | 7/20/2012 | | |
|
|
|
|
Plan assigned to (Tim) | 7/20/2012 | | 7/20/2012 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 7/20/2012 | | 7/20/2012 | | PASS |
Scott Arellano
|
|
|
Plans are approved as shown. Final approval is subject to PDS/Fire field inspection.
|
1st review completed | | | 7/20/2012 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/20/2012 | | |
|
|
|
|
Inspection Record Card- Fire | 7/20/2012 | | 7/20/2012 | | DONE |
Darla L Downs
|
|
|
|
Permit Ready to Issue | | | 7/20/2012 | | |
|
|
|
|
Telephone call | | | 7/20/2012 | | |
|
|
|
7-20-12 called Don-Curtis Fire Sprinkler permit ready and fee give///dld
|