Miscellaneous action | | | 9/23/2013 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 6/3/2013 | 6/5/2013 | 6/5/2013 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 3/12/2013 | 3/13/2013 | 3/13/2013 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro passed
|
INSP-Sprinkler Rough-in | 1/22/2013 | 1/23/2013 | 1/23/2013 | A | PASS |
Troy Cobbley
|
|
|
Sprinkler piping is ok to cover. There are two vertical sections of pipe where the insulator "boxed in" an area to keep the pipe warm. This should work and the building owner and sprinkler contractor are aware of the implications if it should fail and that they are ultimately responcible for keeping the piping above 40 degrees.
|
INSP-Sprinkler Rough-in | 1/16/2013 | 1/22/2013 | 1/23/2013 | A | PASS |
Troy Cobbley
|
|
|
Piping is ok to cover.
|
Plan assigned to (Tim) | 8/6/2012 | | 12/18/2012 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 12/18/2012 | | 12/18/2012 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/18/2012 | | DONE |
Tim Frost
|
|
|
|
Telephone call | | | 12/18/2012 | | DONE |
Christina Prado
|
|
|
Called Jonathan to advise permit is ready and gave fees due
|
Permit Ready to Issue | | | 12/18/2012 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 12/18/2012 | | 12/18/2012 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 12/18/2012 | | DONE |
|
|
|
|
Plan resubmittals received | | | 12/17/2012 | | DONE |
Christina Prado
|
|
|
received three sets of applications, submittal documents and plans; routed to Tim for review
|
Plan resubmittals received | | | 8/24/2012 | | |
|
|
|
Plans that were recieved for this building were the wrong building need a new set of pland for correct building. Tim notified contractor on 8-29-12//BAS
|
Sprinkler Plan Check | 8/10/2012 | | 8/10/2012 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 8/10/2012 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 8/10/2012 | | DONE |
Tim Frost
|
|
|
Emailed review to contractor
|
Telephone call | | | 8/10/2012 | | DONE |
Tisha Gallop
|
|
|
called Jonothan and left vm denied plans here for pick up.
|
Application received | | | 8/6/2012 | | |
|
|
|
|