Miscellaneous action | | | 9/23/2013 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 4/10/2013 | 4/10/2013 | 4/10/2013 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 4/10/2013 | 4/10/2013 | 4/10/2013 | P | PASS |
Troy Cobbley
|
|
|
jonathan Phone #: ###-####
|
INSP-Final Inspection | 4/9/2013 | 4/10/2013 | 4/10/2013 | A | FAIL |
Troy Cobbley
|
|
|
doors are locked no access
|
INSP-Sprinkler Rough-in/Hydro | 2/6/2013 | 2/6/2013 | 2/6/2013 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed
|
INSP-Sprinkler Rough-in | 11/29/2012 | 11/30/2012 | 11/30/2012 | A | PASS |
Troy Cobbley
|
|
|
The first floor breeze-way piping can be covered. The heat tape/insulation has been installed.
|
INSP-Sprinkler Rough-in | 11/21/2012 | 11/21/2012 | 11/21/2012 | P | PASS |
Troy Cobbley
|
|
|
Tenting has been corrected and new plans have been approved. Piping can be covered except for the supply piping that crosses the breeze way at the first floor.
|
Plan assigned to (Tim) | 11/20/2012 | | 11/21/2012 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 11/21/2012 | | 11/21/2012 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/21/2012 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 11/21/2012 | | 11/21/2012 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 11/21/2012 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 11/21/2012 | | DONE |
Christina Prado
|
|
|
Called jonathan to advise permit is ready
|
CHANGE STATUS TO (ISS) | | | 11/21/2012 | | DONE |
Barbara Stitt
|
|
|
|
(F) Reprint permit | | | 11/21/2012 | | DONE |
Barbara Stitt
|
|
|
|
CHANGE STATUS TO (REV) | | | 11/20/2012 | | |
|
|
|
received 3 sets of plans & application for a plan mod///dld
|
INSP-Sprinkler Rough-in | 11/16/2012 | 11/19/2012 | 11/19/2012 | A | FAIL |
Troy Cobbley
|
|
|
See the city approved plans for locations where piping is not covered by the tenting material and heads are blocked by a wall in the restrooms. Also plans need to be resubmitted showing all of the elevation changes, additional elbows and the pipe routing changes.
|
Issue and Print Permit | | | 11/5/2012 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (Tim) | 8/6/2012 | | 8/29/2012 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 8/29/2012 | | 8/29/2012 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/29/2012 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 8/29/2012 | | 8/29/2012 | | DONE |
Darla L Downs
|
|
|
|
Permit Ready to Issue | | | 8/29/2012 | | |
|
|
|
|
Telephone call | | | 8/29/2012 | | |
|
|
|
8-29-12 called JBL Fire left message permit ready and fee given ///dld
|
Plan resubmittals received | | | 8/24/2012 | | |
|
|
|
|
Sprinkler Plan Check | 8/10/2012 | | 8/10/2012 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 8/10/2012 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 8/10/2012 | | DONE |
Tim Frost
|
|
|
Emailed review to contractor
|
Application received | | | 8/6/2012 | | |
|
|
|
|