Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberFIR12-00423
StatusFinaled
Name JBL FIRE PROTECTION LLC
Site Address 1479 S GOLDKING WAY
Project NameUnion Square Apartments Bld10
Customer Number 
ePlanReviewNo
Description
The fire sprinkler scope of work consists of protecting a new three floor apartment building per NFPA 13R. The system is supplied with floor level control valves, 1½” FDC and a 2” Backflow Preventer.

The underground is under permit FIR12-00247
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  9/23/2013 DONE
DetailsTim Frost
Sent to Records for scanning.
INSP-Final Inspection4/10/20134/10/20134/10/2013PPASS
DetailsTroy Cobbley
permit finaled
INSP-Sprinkler Rough-in/Hydro4/10/20134/10/20134/10/2013PPASS
DetailsTroy Cobbley
jonathan Phone #: ###-####
INSP-Final Inspection4/9/20134/10/20134/10/2013AFAIL
DetailsTroy Cobbley
doors are locked no access
INSP-Sprinkler Rough-in/Hydro2/6/20132/6/20132/6/2013PPASS
DetailsTroy Cobbley
Overhead hydro test passed
INSP-Sprinkler Rough-in11/29/201211/30/201211/30/2012APASS
DetailsTroy Cobbley
The first floor breeze-way piping can be covered. The heat tape/insulation has been installed.
INSP-Sprinkler Rough-in11/21/201211/21/201211/21/2012PPASS
DetailsTroy Cobbley
Tenting has been corrected and new plans have been approved. Piping can be covered except for the supply piping that crosses the breeze way at the first floor.
Plan assigned to (Tim)11/20/2012 11/21/2012 DONE
DetailsTim Frost
Sprinkler Plan Check11/21/2012 11/21/2012 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
PLANS/APPL TAKEN TO FRONT DESK  11/21/2012 DONE
DetailsTim Frost
Inspection Record Card- Fire11/21/2012 11/21/2012 DONE
DetailsChristina Prado
Permit Ready to Issue  11/21/2012 DONE
DetailsChristina Prado
Telephone call  11/21/2012 DONE
DetailsChristina Prado
Called jonathan to advise permit is ready
CHANGE STATUS TO (ISS)  11/21/2012 DONE
DetailsBarbara Stitt
(F) Reprint permit  11/21/2012 DONE
DetailsBarbara Stitt
CHANGE STATUS TO (REV)  11/20/2012  
received 3 sets of plans & application for a plan mod///dld
INSP-Sprinkler Rough-in11/16/201211/19/201211/19/2012AFAIL
DetailsTroy Cobbley
See the city approved plans for locations where piping is not covered by the tenting material and heads are blocked by a wall in the restrooms. Also plans need to be resubmitted showing all of the elevation changes, additional elbows and the pipe routing changes.
Issue and Print Permit  11/5/2012 DONE
DetailsBarbara Stitt
Plan assigned to (Tim)8/6/2012 8/29/2012 DONE
DetailsTim Frost
Sprinkler Plan Check8/29/2012 8/29/2012 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
PLANS/APPL TAKEN TO FRONT DESK  8/29/2012 DONE
DetailsTim Frost
Inspection Record Card- Fire8/29/2012 8/29/2012 DONE
DetailsDarla L Downs
Permit Ready to Issue  8/29/2012  
Telephone call  8/29/2012  
8-29-12 called JBL Fire left message permit ready and fee given ///dld
Plan resubmittals received  8/24/2012  
Sprinkler Plan Check8/10/2012 8/10/2012 FAIL
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
1st review completed  8/10/2012 FAIL
DetailsTim Frost
Miscellaneous action  8/10/2012 DONE
DetailsTim Frost
Emailed review to contractor
Application received  8/6/2012